Fire District Approves Construction Manager for New Station, Targets May 5 Bid Opening

Spread the love

The Manhattan Fire Protection District selected ICI Build as its construction management company for the new fire station project and is targeting May 5 for opening construction bids.

The board unanimously approved ICI Build with a 9.5% fee structure during Monday’s meeting, after tabling the decision last month while fee schedules were finalized. The company will provide a full-time supervisor on site throughout the construction process.

“ICI Build will provide a full time supervisor on site at all times,” according to the meeting minutes. Attorney John Motylinski reviewed the contract and made minor procedural changes before the board’s approval.

Chief Steve Malone reported that water and sewer installation for the new station is currently underway as part of the district’s intergovernmental agreement, with ARPA grant funds covering costs. Once the construction management contract is finalized, ICI Build will develop a scope of work and bid package.

The district’s attorney is working with an easement homeowner on final details, and a permit has been submitted to the Village of Manhattan. The Eastern Avenue project should be complete by the end of the year.

In other financial news, the district’s ambulance fees are up 3% overall through the first quarter, while interest rates continue to perform well. No tax revenue has been received yet, which is typical since property tax payments arrive in June.

The board also approved two other significant items during the meeting. Members unanimously approved the final FY2023 audit report, which had been presented in draft form last month, and adopted Ordinance 2025-01 requiring direct connection of fire alarm and detection systems to Laraway Communications Center rather than third-party services.

The district received a $33,000 grant from Earthrise to purchase brush fire personal protective equipment. Deputy Chief Dave Piper is coordinating additional grants, including working with five local pipelines to purchase four-gas monitors for hazardous material detection.

Emergency call volume remains strong with 166 emergency runs last month out of 216 total calls, indicating significant non-emergency activity as well. The district is continuing to address staffing transitions, with recent training completed for nine new part-time members and four interns, though 3-4 members are departing for full-time positions at other departments.

The operational procedures and policy manual with Lexipol is approximately 95% complete, with the attorney reviewing chapters for consistency with the collective bargaining agreement and union executive board reviewing policies. The complete manual will be presented to the board for adoption once finalized.

Latest News Stories

Will County Board Land Use Committee Graphic.3

Will Land Use Committee Evaluates Multi-Million Dollar Buyout for Flooded Harris Drive Homes

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: The Will County Land Use and Development Committee is exploring a multi-million-dollar buyout program for several homes...
Will County Board Graphic.04

Behavioral Health Division Drops Wait Times, Reports Zero Opioid Deaths in February

Public Health & Safety Committee Meeting | March 5, 2026 Article Summary: Will County’s Behavioral Health Division reported significant operational improvements, including a near-elimination of wait times for therapy and...
Will County Board Graphic.03

Harris Drive Residents Plead for County Intervention Amid Failing Septic Systems and Flooding

Public Health & Safety Committee Meeting | March 5, 2026 Article Summary: Residents of Harris Drive appealed to the Public Health and Safety Committee for help with severe seasonal flooding...
Police Crime

Will County Sheriff’s Office Investigates Fatal Hit-and-Run in Homer Glen

Article Summary: The Will County Sheriff’s Office is seeking the public's assistance in identifying a driver involved in a fatal hit-and-run crash in Homer Glen that left a pedestrian dead....
will county Committee-Public Health & Safety.Graphic

Federal Funding Freezes Threaten Will County Public Health Programs Amid Ongoing Lawsuits

Public Health & Safety Committee Meeting | March 5, 2026 Article Summary: Will County health officials are bracing for potential service disruptions as they monitor multiple federal lawsuits surrounding frozen...
Will County Board Federal Agenda

Board Splits Along Party Lines to Approve 2026 Federal Legislative Agenda

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board adopted its 2026 Federal Legislative Agenda in a 10-9 vote, establishing the county's priorities for lobbying efforts...
Vice President of the Peotone Teachers Union addressed the board on March 2-photo by Andrea Arens.

Peotone 207U Board Votes to Close Intermediate School for 2026–27

By Andrea Arens In a unanimous vote, the Peotone Community Unit School District 207U Board of Education approved a resolution to close Peotone Intermediate School beginning with the 2026–27 school...
Will County Board Graphic.01

Meeting Summary and Briefs: Will County Landfill Committee for February 10, 2026

Will County Landfill Committee Meeting | February 10, 2026 The Will County Landfill Committee met on Tuesday to address legal preparations for the upcoming landfill expansion and operational needs at...
Will County Board Graphic.04

Board Approves Joliet Township Clean Fill Facility Despite Environmental Objections

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board approved a map amendment and special use permit for a Clean Construction and Demolition Debris (CCDD) facility...
Will County Board Graphic.03

Meeting Summary and Briefs: Will County Board for February 19, 2026

Will County Board Meeting | February 19, 2026 Meeting SummaryThe Will County Board meeting on Thursday, February 19, 2026, was marked by significant zoning decisions, including the unanimous rejection of...
solar panels photovoltaics in solar farm

Will County Board Unanimously Rejects Controversial Solar Farm in Troy Township

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board unanimously rejected a special use permit for a commercial solar energy facility near Shorewood following strong opposition...
Will County Board Graphic.03

Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Will County Landfill Committee Meeting | February 10, 2026 Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to...
Will County Board Graphic.04

County Approves $1.9 Million for Wilmington-Peotone Road Engineering

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board authorized nearly $2 million in Motor Fuel Tax funds to begin Phase I design engineering for improvements...
Police Crime

County Board Authorizes Audit of Homer Glen Policing Contract; Officials Seek ‘True Cost’ of Services

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board unanimously approved a $75,000 contract to audit the cost of law enforcement services provided to the Village...
Will County Board Graphic.01

Landscape Business Approved on Cedar Road Despite ‘Dangerous Curve’ Concerns

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board approved a special use permit for a landscape business on Cedar Road in Homer Glen, despite concerns...