Solar Project Extensions Approved as Industry Faces Permitting Delays
Three solar energy projects received 180-day extensions from Will County’s Land Use & Development Committee Thursday as developers continue working through lengthy permitting processes with utility companies and other agencies.
The extensions cover projects in Peotone, Channahon, and Crete townships that received special use permits in 2023 but haven’t yet obtained building permits. Under county rules, special use permits expire within two years unless construction permits are issued.
A Peotone Township solar project by Turning Point Energy received its extension after experiencing delays with updated conservation plans and changing fire district requirements. Joseph Chessup, representing the developer, said soil and water conservation standards were updated last year, requiring them to restart their conservation planning process.
The Manhattan Fire Protection District also changed safety standards as recently as May 20, requiring wider access roads and higher weight capacity to accommodate 80,000-pound fire equipment.
“There’s been a few unexpected delays with getting the permits finalized for this project,” Chessup said.
Staff also provided an update on solar interconnection requirements after meeting with ComEd officials. The utility company clarified that they don’t require above-ground power connections for solar projects, contrary to claims made by some developers.
ComEd uses a five-step process taking about 180 days for interconnection agreements. While they typically install four riser poles for connections, they can accommodate underground lines for 12KV systems, though 34KV lines remain economically impractical to bury.
The committee expressed interest in requiring more underground infrastructure for future solar projects to preserve rural aesthetics. “I would like to see us have them put it underground as much as they possibly can,” said Committee member Judy Ogala.
Latest News Stories
Federal Lobbyists Brief Will County on Government Shutdown, Warn of SNAP and TSA Disruptions
Will County Committee Advances Gougar Road Bridge Project with Over $540,000 in Agreements
Commission Approves Mokena-Area Garage Variance Over Village’s Objection
Residents Clash on School Funding, Citing Low Tax Rate vs. “Wasteful” Spending at Committee Meeting
JJC Receives Surprise $1.9 Million from IRS Employee Retention Credit
JJC Advances ERP Modernization with New Vendor and Two-Year Budget
Will County Committee Shapes 2026 Legislative Agendas on Housing, Energy, and Health
JJC Authorizes Land Buy for Grundy County Expansion, Secures Site in Morris
Commission Grants Green Garden Solar Farm Project Variance Extension
Peotone School Committee: Issue $4.85M Bond to Cover Deficit, Maxing Out Debt Capacity
Will County Committee Advances Phased Takeover of Central Will Dial-A-Ride Service
Everyday Economics: Rate cut debate: Reading mixed signals in a fragile economy