Summer Construction Projects Transforming Peotone Schools

Major construction projects are progressing on schedule across Peotone School District 207-U, with significant HVAC upgrades, new secure entrances, and extensive paving work transforming campuses ahead of the new school year.

Facilities director Mike Singleton provided the Board of Education with a detailed update on the summer’s work during its July 21 meeting. The removal of the mobile classroom units at Peotone Junior High School is complete, and large-scale mechanical projects are well underway.

At Peotone High School, a new chiller has been installed, with the factory startup scheduled for the following day. At Peotone Elementary School, a 150-foot crane was recently on-site to lift new rooftop HVAC units into place. Inside, the installation of copper piping is 100% complete and duct work is approximately 85% finished, keeping the project on track for a phased turnover to cleaning crews starting in early August.

The district’s security is also being enhanced with the installation of new secure vestibules. The inner set of doors at the junior high has been installed, with the outer doors and new concrete work scheduled for the coming weeks. Similar work is being completed at Peotone Elementary and Peotone Intermediate Center.

Additionally, extensive concrete patching and seal coating have been completed or are in progress at the junior high, high school, and Connor Shaw Center, refreshing the appearance and safety of parking lots and drop-off areas. While the projects create a tight turnaround for teachers to prepare classrooms, administrators are “very cautiously optimistic” that all buildings will be ready for the start of school.

Events

No events

Latest News Stories

Screenshot-2025-06-16-at-3.26.08-PM-1

Will County Board Meeting Briefs Package

COUNTY APPOINTMENTS Fire Protection District: Board approved county executive appointments to Manhattan Fire Protection District board. Agricultural Committee: Approved appointment to Agricultural Area Committee with Member Judy Ogala abstaining due...
frankfort-park-district.1

Frankfort Park District Reorganizes Board, Explores Options for Tax-Impacting Projects

FRANKFORT – The Frankfort Park District Board seated its re-elected members, reorganized its leadership, and approved its new annual budget on Tuesday, while also revealing it is actively exploring options...
frankfort-park-district

Aging Sara Park Building Poses Challenge for Park District

The Frankfort Park District is grappling with how to address the deteriorating Sara Park building, whose roof is in "bad shape" and whose location within a flood plain complicates any...
frankfort-park-district.1

Meeting Briefs: Frankfort Park District Board for May 13, 2025

The Frankfort Park District Board of Commissioners re-elected its leadership team for a new term and approved its fiscal year 2025-2026 budget at its meeting on Tuesday. The board also...
Green-Garden-Logo.WP

Township Board Unites Against State Consolidation Efforts

GREEN GARDEN TOWNSHIP — The Green Garden Township Board voted unanimously to oppose state legislation that would consolidate township governments, amending the Annual Town Meeting agenda to include a resolution...
Green-Garden-Logo.WP

Planning Commission Outlines Three-Step Process for Land Use Plan

GREEN GARDEN TOWNSHIP — The Green Garden Township Planning Commission has established a three-step process for developing the township's new land use plan, with public input opportunities scheduled throughout spring,...
Green-Garden-Logo.WP

Road Projects Face Delays as Commissioner Reports Solar Leases on Needed Land

GREEN GARDEN TOWNSHIP — The planned Sheer Road bridge replacement project has been pushed back to 2026 due to utility issues, and negotiations for needed easements are complicated by solar...
Green-Garden-Logo.WP

Green Garden Township News Briefs – March 2025

Township Property Values Continue Rising: Assessor Bushong reported Green Garden Township's equalized assessed value (EAV) continues to grow rapidly, increasing by $2.5 million in just the first two months of...
Peotone-High-School-scaled-2

Peotone School Board Approves New Curriculum, Welcomes New Administrators

The Peotone Community Unit School District 207U Board of Education approved a new K-5 English Language Arts curriculum and introduced two new administrators during its April 23 meeting at Peotone...
Peotone-School-District

Peotone Students Honored for Academic and Athletic Achievements

The Peotone Board of Education recognized numerous students for their academic and athletic accomplishments during the April 23 meeting. High school sophomore Olivia Robinson was honored as the March Student...
Peotone-Junior-High-School-scaled-2

Peotone School Board Meeting Briefs

Grant Funding Secured: The district received approval for a $2,250 Illinois Literacy Plan Grant to support professional development for the new K-5 ELA curriculum implementation. Combined with $6,200 from an...
MFPD-Logo-Fire-District-3

Fire District Approves Construction Manager for New Station, Targets May 5 Bid Opening

The Manhattan Fire Protection District selected ICI Build as its construction management company for the new fire station project and is targeting May 5 for opening construction bids. The board...
MFPD-Logo-Fire-District-15

Fire District Approves Construction Manager for New Station, Targets May 5 Bid Opening

The Manhattan Fire Protection District selected ICI Build as its construction management company for the new fire station project and is targeting May 5 for opening construction bids. The board...
MFPD-Logo-Fire-District-19

Fire District Expands Health Programs, Considers Cancer Screening

The Manhattan Fire Protection District is expanding its employee wellness initiatives with potential cancer screening through body scans and continuing its successful injury prevention program. The Health and Safety Committee...
MFPD-Logo-Fire-District-4

Fire District Expands Health Programs, Considers Cancer Screening

The Manhattan Fire Protection District is expanding its employee wellness initiatives with potential cancer screening through body scans and continuing its successful injury prevention program. The Health and Safety Committee...