Summer Construction Projects Transforming Peotone Schools
Major construction projects are progressing on schedule across Peotone School District 207-U, with significant HVAC upgrades, new secure entrances, and extensive paving work transforming campuses ahead of the new school year.
Facilities director Mike Singleton provided the Board of Education with a detailed update on the summer’s work during its July 21 meeting. The removal of the mobile classroom units at Peotone Junior High School is complete, and large-scale mechanical projects are well underway.
At Peotone High School, a new chiller has been installed, with the factory startup scheduled for the following day. At Peotone Elementary School, a 150-foot crane was recently on-site to lift new rooftop HVAC units into place. Inside, the installation of copper piping is 100% complete and duct work is approximately 85% finished, keeping the project on track for a phased turnover to cleaning crews starting in early August.
The district’s security is also being enhanced with the installation of new secure vestibules. The inner set of doors at the junior high has been installed, with the outer doors and new concrete work scheduled for the coming weeks. Similar work is being completed at Peotone Elementary and Peotone Intermediate Center.
Additionally, extensive concrete patching and seal coating have been completed or are in progress at the junior high, high school, and Connor Shaw Center, refreshing the appearance and safety of parking lots and drop-off areas. While the projects create a tight turnaround for teachers to prepare classrooms, administrators are “very cautiously optimistic” that all buildings will be ready for the start of school.
Latest News Stories

County Rep Cites Solar Lawsuits, Grant Shortfalls as Key Issues Facing Will County

Assessor’s Office Hires Staff to Handle Workload After 6% Multiplier Hits Property Owners

Township Appoints Temporary FOIA Officer During Trustee’s Leave of Absence

Meeting Summary and Briefs: Green Garden Township Board for August 11, 2025

WATCH: Illinois In Focus Daily | Tuesday Aug. 12th, 2025

Governor to evaluate tax proposal for Bears stadium in Arlington Heights

Illinois quick hits: Report shows rate of businesses leaving state

Report: New York No. 2 in nation for inbound tobacco smuggling

Trump delays China tariffs by 90 days

Kennedy visits Atlanta’s CDC

DCFS denies claim that agency uses uncertified interns to investigate families

Trump declares ‘Liberation Day’ in D.C., calls in National Guard