Road Projects Face Delays as Commissioner Reports Solar Leases on Needed Land
GREEN GARDEN TOWNSHIP — The planned Sheer Road bridge replacement project has been pushed back to 2026 due to utility issues, and negotiations for needed easements are complicated by solar farm leases on adjacent properties, Road Commissioner Jim Hilliard reported at the March township board meeting.
“Sheer Road bridge setback due to Com Ed utility poles not being moved until September moving completion into 2026,” Hilliard explained in his report to the board. The project has already undergone engineering and planning, but the utility delays will push construction back by approximately a year.
Complicating matters further, Hilliard reported challenges in “negotiating with landowners easements for Sheer Road bridge in which three parcels have leases for solar.” When questioned by Supervisor Murday about whether the leases were purchased, Hilliard responded that “the deeds from the County showed filed lease with the landowner and landowner did not want to discuss.”
This information led to questions from township officials about potential unknown solar development. Murday stated his purpose in asking was “to see what else is looming out there that the Township has no knowledge of pertaining to solar farms.” He requested parcel numbers to track the properties and expressed concern “there are lease agreements out there that we have no knowledge of.”
Hilliard also reported that bids will soon go out for a box culvert project on Dralle Road and for repairs to roads that are “falling apart.” His update included information on routine maintenance activities, including in-house body work on trucks, removing plow equipment and cleaning, trimming trees, and clearing ditches.
In response to resident Buddy Schultz’s repeated complaints about the flagpole at the township garage, Hilliard stated he “would love to replace and will price it out for next meeting.” Schultz, who raised the issue during public comments, indicated he “would like a new one and pole and is willing to purchase the flag.”
Resident Linda Owens inquired about “the grant for solar lights on stop signs and if it was going to happen,” though the minutes do not record Hilliard’s specific response to this question.
Latest News Stories
Will County Committee Grants Extensions for Crete, Washington Township Solar Projects
Meeting Summary and Briefs: Green Garden Township for November 10, 2025
Illinois patient relies on ACA tax credits, experts warn they drive higher premiums
Chicago mayor threatens layoffs, property tax hikes if council rejects head tax
Illinois quick hits: Four officers injured during ICE protest
Will County Committee Denies Appeal for Crete Township ‘Tiny Home’ Permit
Judge: Biden-era decree deal requires release of 600+ from ICE detention
Green Garden Township Sets $1,000 Monthly Cap for General Assistance Program
New Lenox Solar Farm Gains County Committee Approval with Conditions
Committee Approves Frankfort Township Gaming Bar on Split Vote
Crete Township Senior Group Home Gets Unanimous Committee Support
Beecher-Area Rezoning and Variances Approved to Legalize Structure
Committee Approves Wilton Township Land Division Despite Spot Zoning Concerns