Second Solar Farm with Battery Storage Proposed in Green Garden
Article Summary: A second, separate commercial solar project has been proposed in Green Garden Township by Turning Point Energy, adding to residents’ growing concerns about farmland being converted for energy production. The new 72-acre proposal, located at Stunkle and LaGrange Roads, would include battery storage and is projected for 2026.
Turning Point Solar Proposal Key Points:
-
Project Details: The facility would cover approximately 72 acres with 14,000 solar panels and include a battery storage component consisting of eight 20-foot trailers.
-
Location: The proposed site consists of two triangular parcels at the intersection of Stunkle and LaGrange Roads.
-
Developer: The project is proposed by Turning Point Energy, the same company behind a previous solar installation in the township.
GREEN GARDEN TOWNSHIP — As residents mobilize against one massive solar project, Green Garden Township officials revealed that a second, unrelated solar farm is being proposed by a different developer.
Trustee Ralph Deetsz reported during Monday’s board meeting that he and Trustee Monroe Striggow met with representatives from Turning Point Energy on August 28 to discuss a new solar facility with battery storage. The project, nicknamed “Turning Point Two” by Deetsz, would be located on two triangular parcels totaling 72 acres at Stunkle and LaGrange Roads.
The proposal includes approximately 14,000 solar panels and a battery storage system housed in eight 20-foot trailers. Deetsz said the representative, Scott Osborne, indicated the project is planned for 2026 and an application has not yet been filed with the county.
This new proposal is entirely separate from the 600-megawatt facility proposed by Earthwise, which has become a major point of contention in the community. Turning Point Energy previously developed another solar farm in the township.
Deetsz noted that the new project’s location on Stunkle Road could be a factor in its approval, as the board has previously expressed a desire to limit development along that corridor. The proposal adds another layer to the ongoing debate over land use and renewable energy development in the rural township.
Latest News Stories
Resident Alleges Financial Mismanagement, Underused Buildings at Peotone Board Meeting
Meeting Briefs: Peotone School District 207-U for July 21, 2025
Crete Township Wins Approval for New Digital Sign at Community Center
Will County Planners OK Oversized Garage Near Naperville, Overriding Staff Recommendation
Green Garden Landscaping Business Gains Permit Amid Strong Neighbor Support
Meeting Briefs: Will County Planning and Zoning Commission for July 15, 2025
Frankfort Approves ‘Whisk & Flame’ Culinary Studio, Slashes Parking Requirement for Downtown Property
Frankfort Village Board Adopts $59.4 Million Appropriation for Fiscal Year 2026
Frankfort Establishes New Zoning Rules to Attract Data Centers
Currie Motors Expansion Gets Approval with Site Modifications
Frankfort Approves $134,531 Maintenance Contract for Wastewater Plant Filters
Meeting Briefs: Frankfort Village Board for July 14, 2025