solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Spread the love

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy developers. The new operators, Nautilus Solar and Madison Energy Infrastructure, now have until 2026 to begin construction as they work to secure final permits.

Solar Project Sales Key Points:

  • Projects Involved: Five separate solar farms in Peotone, Monee, Crete, and Joliet townships received 180-day extensions.

  • New Developers: Two projects were sold to Nautilus Solar, and three were sold to Madison Energy Infrastructure.

  • Action: The extensions give the new owners until February or April 2026 to secure construction permits and lawfully establish the facilities.

  • Status: While required variances for the projects have been established, construction permits submitted by the new developers remain under review by the county.

JOLIET — A pattern of smaller solar energy projects being sold to larger developers has prompted the Will County Board to grant permit extensions for five separate solar farms. The board unanimously approved the first 180-day extensions for the projects, which are now owned by Nautilus Solar and Madison Energy Infrastructure.

According to county memos, the original applicants for all five projects had successfully established required variances related to ground cover and mowing, but the special use permits were nearing their two-year expiration dates. The projects were subsequently sold to the new developers, who have since applied for construction permits that are still under review.

Nautilus Solar acquired two projects:

  • A facility from Aequo Foundation, Inc. on Kennedy Road in Peotone.

  • A facility from Felipe D. Recendez on South Will Center Road in Monee.
    Both permits are now valid through April 17, 2026.

Madison Energy Infrastructure acquired three projects:

  • Two facilities from Dart Farms, Inc. in Joliet Township at the northwest and southwest corners of Cherry Hill Road and W. Schweitzer Road/US 52.

  • A facility from The Moeller Trust on Torrence Avenue in Crete.
    These permits are now valid through February 13, 2026.

The board’s approval of the extensions provides the new operators additional time to finalize the permitting process and begin construction on the renewable energy facilities.

Leave a Comment





Latest News Stories

Meeting-Briefs

Will County Finance Committee July 1 Meeting Briefs

Bond Refinancing Advances: Finance Committee approved an ordinance authorizing up to $200.8 million in bond refinancing that could save taxpayers more than $716,000. The measure moves to the full County...
Meeting-Briefs

Will County Public Works Committee Juliy 1 Meeting Briefs

ROAD CONTRACTS APPROVED Austin Tyler Construction Contract: The committee approved a $691,544 contract with Austin Tyler Construction for resurfacing River Road from East Frontage Road to Prairie Creek Bridge and...
Screenshot 2025-07-08 at 2.34.06 PM

Green Garden Township Weighs Youth Sports Partnership for Community Development

Green Garden Township could become home to expanded youth football facilities under a proposal presented at Thursday's special meeting, as local sports programs seek permanent venues amid community facility discussions....
Meeting-Briefs-1

Green Garden Town Hall June 26 Meeting Briefs

Grant Deadline Approaches: Green Garden Township must decide on facility plans by the end of 2026 to retain $400,000 in remaining Will County grant funding. The township has already invested...
JJC-Graphic-Logo

JJC Trustees Approve Contentious FY26 Budget After Heated Debate, Failed Postponement

The Joliet Junior College Board of Trustees on Wednesday approved a $322.3 million budget for fiscal year 2026, but not before a tense debate that saw a motion to postpone...
Joliet-Junior-college.-Graphic-Logo.5

JJC’s ‘12x12x12’ Initiative Boosts College Credits, Increases Matriculation Rate

Joliet Junior College’s ambitious "12x12x12" initiative is yielding significant results, leading to more high school students earning college credits and a greater percentage of them choosing to attend JJC after...
Joliet-Junior-college.-Graphic-Logo.4

JJC Board Meeting Highlights Tensions Over Legal Bills, Trustee Conduct

An otherwise routine vote to approve monthly bill payments ignited a tense exchange at the Joliet Junior College Board of Trustees meeting Wednesday, revealing ongoing friction over redacted legal invoices,...
Joliet-Junior-college.-Graphic-Logo.3

Students, Trustees Emphasize Importance of Inclusivity and Flag Raisings at JJC

From a recent graduate’s public plea to trustee remarks on federal policies, the theme of student belonging and inclusivity was a prominent thread at the Joliet Junior College Board of...
Joliet-Junior-college.-Graphic-Logo.2

JJC Embarks on New 10-15 Year Facilities Master Plan Process

Joliet Junior College is laying the groundwork for its physical future, officially launching a comprehensive process to create a new facilities master plan that will guide campus development for the...
Meeting-Briefs

Meeting Summary: Joliet Junior College Board of Trustees for June 25, 2025

The Joliet Junior College Board of Trustees met on Wednesday, June 25, 2025. Key actions included the approval of the fiscal year 2026 budget after a contentious debate and hearing...
Will-County-Board-Meeting-June-18-2025

Will County Board Halts Transportation Plan After Contentious 143rd Street Debate

The Will County Board voted Wednesday to send its five-year, multi-million dollar transportation improvement plan back to committee, effectively pausing all projects after a lengthy and heated debate over the...
Will-County-Board-Meeting-June-18-2025

Will County Board Upholds Zoning Denials, Rejecting Developer Appeals

The Will County Board on Wednesday backed its Planning and Zoning Commission (PZC), denying two separate appeals from property owners who sought to overturn the commission’s recommendations against their projects....
Will-County-Board-Meeting-June-18-2025

Split Vote Halts Monee Truck Terminal Project

A proposed truck terminal on vacant land at West Monee-Manhattan Road in Monee Township was stopped in its tracks Wednesday after the Will County Board delivered a split decision on...
Will-County-Board-Meeting-June-18-2025

Future Quarry Fight Looms as Board Approves ‘Tequila Barrel’ Retreat

While the Will County Board greenlit a unique tourist destination featuring overnight stays in repurposed tequila barrels, it also received formal notice of a coming fight to shut down a...
Meeting-Briefs

News Briefs from the Will County Board June 18 Meeting

Monee Church Designated Historic LandmarkThe Will County Board unanimously voted to designate St. Paul's United Church of Christ in Monee as a historical landmark. Member Judy Ogalla, a Monee native,...