Will County Finance Committee Meeting October 7, 2025

Article Summary: Will County’s Renewable Natural Gas (RNG) plant at the county landfill posted a net loss of nearly $460,000 for the fiscal year through August, after a summer plagued by mechanical failures, power outages, and maintenance issues that hampered production. Despite the challenges, officials remain optimistic about closing the financial gap by the end of the fiscal year, pointing to a strong performance in September and the plant’s long-term revenue potential.

RNG Plant Performance Key Points:

  • As of August 31, 2025, the RNG plant reported a net loss of $459,484.52 for the fiscal year.

  • Production in July and August fell below targets due to valve failures, sensor issues, severe storms, and computer errors.

  • Production exceeded targets in June, and a strong rebound in September has officials hopeful of breaking even for the year.

  • The plant is in its third year of repaying a 12-year, $48 million green bond used for its construction.

JOLIET, IL – Will County’s gas-to-energy plant has faced a series of operational challenges this summer, resulting in a net loss of $459,484 as of August 31, according to a report presented to the Finance Committee on Tuesday, October 7, 2025.

Greg Komperda, the RNG Facility Project Manager, detailed a difficult summer for the plant, which converts landfill gas into pipeline-quality natural gas. While production in June exceeded its target, generating over 73,000 Million British Thermal Units (MMBtu), performance dipped significantly in July and August.

In July, the plant produced 68,768 MMBtu against a target of 71,300 MMBtu. August production fell further to 64,446 MMBtu. Komperda attributed the shortfalls to a string of problems, including:

  • Valve failures in the nitrogen removal system, likely caused by moisture in the compressed air supply.

  • A delivery rejection from the pipeline operator due to faulty sensors at the delivery point.

  • Ongoing landfill wellfield maintenance, which temporarily reduced the flow of gas to the plant.

  • Sporadic power outages caused by severe storms in late August.

  • Computer errors in the nitrogen control system that required the manufacturer to reprogram it.

Despite the setbacks, Komperda reported that production rebounded in September to over 69,000 MMBtu. “We are closing in on the gap,” he said. “If we could maintain production at a good level, we have a chance of closing that gap in on our under revenue.”

Board members questioned the operational reliability and long-term financial viability of the project. In response to questions about frequent power outages, officials stated that installing a backup generator system capable of powering the plant was not financially feasible. Similarly, a significant solar array to offset the plant’s high electricity consumption—more than all other county facilities combined—would require 70-80 acres and cost an estimated $28 to $48 million.

Board member Daniel J. Butler highlighted the project’s long-term investment perspective. He confirmed with officials that the plant was financed with a 12-year, $48 million green bond. With three years of payments made, the facility has nine years of debt service remaining.

“After 12 years, we are going to be having generate extra money and it should lessen the tax burden,” Butler said, framing the current challenges within the context of the plant’s projected 35-plus-year lifespan. “Here we are making an investment into the future for the people of Will County.”

Leave a Comment





Latest News Stories

Independent tax tribunal faces elimination by Pritzker budget proposal

Independent tax tribunal faces elimination by Pritzker budget proposal

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – The chief judge of the Illinois Independent Tax Tribunal says it will be bad for taxpayers if...
Illinois Quick Hits: Civic federation funds 'persistent structural imbalance' in Illinois

Illinois Quick Hits: Civic federation funds ‘persistent structural imbalance’ in Illinois

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – A new Civic Federation report has identified a persistent structural imbalance in the Illinois budget, with expenditures...
Will County Board Graphic.01

Millions Approved for Will County Highway and Road Infrastructure Projects

Will County Board Meeting | April 16, 2026 Article Summary: The Will County Board authorized nearly $4.3 million in road improvement contracts, targeting key corridors including Francis Road, Renwick Road,...
Illinoisans may soon need registration, title, license to use e-bikes, scooters

Illinoisans may soon need registration, title, license to use e-bikes, scooters

By Sean Reed | The Center SquareThe Center Square (The Center Square) – Illinoisans may soon be required to register their e-bikes, motorized scooters and other various modes of transport...
Pritzker’s commission report pushes for local investigations of federal 'brutality'

Pritzker’s commission report pushes for local investigations of federal ‘brutality’

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Gov. J.B. Pritzker’s Illinois Accountability Commission has released its report on alleged abuses by federal immigration law...
Illinois mulls change allowing pension investment in anti-Israel companies

Illinois mulls change allowing pension investment in anti-Israel companies

By Sean Reed | The Center SquareThe Center Square (The Center Square) – Multiple speakers shared personal stories Thursday from the conflict between Israeli forces and Palestinians in an effort...
Will County Board Graphic.04

Board Establishes New Regulations and Fees for Wireless Telecommunication Facilities

Will County Board Meeting | April 16, 2026 Article Summary: In response to the state's Small Wireless Facilities Deployment Act, the Will County Board passed Ordinance 26-134 to manage the...
Joseph House

Historic Joseph Perry House in Crete Granted Landmark Status

Will County Board Meeting | April 16, 2026 Article Summary: The Will County Board officially designated the Joseph Ferris Perry House in Crete Township as a historical landmark, protecting the...
Will County Board Graphic.02

Will County Passes Comprehensive Adult Entertainment Ordinance

Will County Board Meeting | April 16, 2026 Article Summary: The Will County Board passed Ordinance 26-133, enacting Chapter 119 of the Business Regulations to establish rigorous licensing, operational, and...
Will County Board Graphic.03

Will County Takes Jurisdiction of Countyline Road in $1.84 Million Agreement with Kankakee County

Will County Board Meeting | April 16, 2026 Article Summary: The Will County Board has approved a jurisdictional transfer that brings a 4.27-mile stretch of Countyline Road entirely under Will...
Will County Board Graphic.01

Green Garden Township’s Wildflower Farm Granted Third Special Use Extension

Will County Board Meeting | April 16, 2026 Article Summary: Bengston Land Management, LLC secured a third extension on its special use permit to host rural events at The Wildflower...
Will County Board Graphic.04

Will County Board Approves Controversial Solar Farms Following Court Mandate

Will County Board Meeting | April 16, 2026 Article Summary: Under the strict constraints of a court-issued writ of mandamus, the Will County Board grudgingly approved multiple special use permits...
(Photo by Chad Merda)

Oldest preserve expansion pushes acreage past 24,000 milestone

The Forest Preserve’s first acquisition of the year not only expands the District’s oldest preserve, it also pushes total acreage past the 24,000 mark. On March 27, the Forest Preserve...
Will County Board Graphic.04

Meeting Summary and Briefs: Will County Board Executive Committee for April 9, 2026

Will County Board Executive Committee Meeting | April 9, 2026 The Will County Board Executive Committee met on Thursday, April 9, 2026, to process a diverse agenda featuring major strategic,...
Rock Run Preserve —Photo by Chad Merda

On the road to 100 years: How the Forest Preserve District expanded

As the Forest Preserve District approaches its centennial year in 2027 with a total of nearly 24,000 protected acres, it’s a good time to reflect on how the District grew...