Will County Committee Grants Extensions for Crete, Washington Township Solar Projects

Spread the love

Will County Land Use & Development Committee Meeting | November 6, 2025

Article Summary: The Will County Land Use and Development Committee granted 180-day extensions for two commercial solar energy projects in Crete and Washington Townships, giving the developer additional time to complete the necessary permitting before their initial approvals expire.

Solar Farm Permit Extensions Key Points:

  • A first extension was approved for a TPE Development affiliated project in Crete Township (ZC-23-108), pushing its deadline to June 19, 2026.

  • A first extension was also granted for a related TPE project in Washington Township (ZC-24-020), moving its deadline to November 12, 2026.

  • The extensions were requested to allow more time to complete complex permitting and pre-construction processes.

  • Special use permits for solar facilities in Will County typically expire after two years if construction has not legally commenced.

JOLIET, IL — Two large-scale solar energy projects in eastern Will County were granted more time to get off the ground after the Will County Land Use and Development Committee on Thursday, November 6, 2025, approved their first 180-day permit extensions.

The committee unanimously approved the requests for projects in Crete and Washington townships, both associated with TPE Development, LLC. The extensions are necessary because the special use permits approved by the County Board are set to expire within the next year, and the projects have not yet completed the building permit process to legally establish the use.

The first extension was for case SEXT-25-019, concerning a commercial solar facility at the southeast corner of South Nacke Road and West Loves Lane in Crete Township. Originally approved on December 21, 2023, the permit was set to expire in December 2025. The applicant has applied for a building permit but cited needing more time to complete the process. The extension is now valid through June 19, 2026.

The second approval was for case SEXT-25-020, for a solar facility at the southeast corner of West Indiana Avenue and South Western Avenue in Washington Township, near Beecher. This project was approved on May 16, 2024, and its permit was set to expire in May 2026. According to county staff, the applicant has not yet applied for a building permit. The extension pushes the new expiration date to November 12, 2026.

Under the Will County Zoning Ordinance, a special use permit lapses after two years if the use has not been legally established. The ordinance allows the County Board to grant up to four separate 180-day extensions for “good cause.” Jordan Belknap, representing the applicant, stated they have been working with local authorities, including University Park, on necessary road improvements for the Crete project before construction can begin.

Leave a Comment





Latest News Stories

Judge sets up high stakes baby formula NEC trial vs Mead Johnson

Judge sets up high stakes baby formula NEC trial vs Mead Johnson

By Jonathan Bilyk | Legal NewslineThe Center Square A federal judge has potentially cleared the way for another trial against pharmaceutical and nutritional supplement maker Mead Johnson & Co. over...
Illinois Quick Hits: Home insurance regulations approved by Illinois Senate

Illinois Quick Hits: Home insurance regulations approved by Illinois Senate

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – A bill to regulate homeowners insurance rates will be up for consideration in the Illinois House after...
Illinois Senate passes bill to regulate auto insurance rates

Illinois Senate passes bill to regulate auto insurance rates

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – The Illinois Senate has approved legislation to regulate auto insurance rates, but a former Illinois Department of...
Op-Ed: The FAA's O'Hare decision is a win for travelers – and for competition

Op-Ed: The FAA’s O’Hare decision is a win for travelers – and for competition

By Mario H. Lopez | Hispanic Leadership FundThe Center Square At Chicago's O'Hare International Airport, one of the nation's most critical travel hubs and a gateway for millions of passengers...
Bill to prevent fraud on elderly, disabled opposed by financial institutions

Bill to prevent fraud on elderly, disabled opposed by financial institutions

By Sean Reed | The Center SquareThe Center Square (The Center Square) – Based on the multiple billions of dollars lost to scams and exploitation of elderly and disabled adults...
Will County Board Graphic.01

Legislative Committee Advances Resolution Opposing Kidney Disease Treatment Delegation Act

Will County Board Legislative Committee Meeting | May 5, 2026 Article SummaryThe Will County Legislative Committee unanimously approved a resolution formally opposing Senate Bill 3445 and House Bill 4402, citing...

Illinois Quick Hits: Gas tops $5 a gallon

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – AAA says the average price for a gallon of regular unleaded gasoline is now $5.03 in Illinois,...
Will County P&Z Logo Planning Zoning.2

Commission Approves Massive Lake Michigan Water Infrastructure Project for Troy Township

Will County Planning and Zoning Commission Meeting | May 5, 2026 Article Summary: The Will County Planning and Zoning Commission on May 5, 2026, unanimously approved two major public utility...
Will County Board Graphic.02

Committee: Capital Improvements Committee Weighs $300 Million Options for Downtown Joliet Campus

Will County Board Capital Improvements & IT Committee Meeting | May 5, 2026 Article SummaryThe Will County Capital Improvements & IT Committee is evaluating four multi-million-dollar proposals to replace aging...
Will County Board Graphic.04

State Legislative Update: Housing Mandates, Mega Projects, and Data Centers Prompt Local Control Concerns

Will County Board Legislative Committee Meeting | May 5, 2026 Article SummaryState lobbyists from Mac Strategies briefed the Will County Board Legislative Committee on the final push of the spring...
Will County Finance Logo

Meeting Summary and Briefs: Will County Board Finance Committee for May 5, 2026

Will County Board Finance Committee Meeting | May 5, 2026 The Will County Board Finance Committee dedicated nearly its entire May 5, 2026, meeting to a series of rapid-fire, preliminary...
Will County Board Graphic.02

Committee Advances Nearly $212,000 in Road and Facility Contracts for Jackson Township and Monee

Will County Board Public Works & Transportation Committee Meeting | May 5, 2026 Article SummaryThe Will County Public Works and Transportation Committee approved two infrastructure contracts totaling over $212,000 for...
Will County Board Graphic.03

Will County Committee Hits Brakes on License Plate Reader Agreements Awaiting Privacy Policy Review

Will County Board Public Works & Transportation Committee Meeting | May 5, 2026 Article SummaryThe Will County Public Works and Transportation Committee delayed votes on five intergovernmental agreements for Automated...
Will County Board Graphic.03

Meeting Summary and Briefs: Will County Board Capital Improvements & IT Committee for May 5, 2026

Will County Board Capital Improvements & IT Committee Meeting | May 5, 2026 The Will County Board Capital Improvements & IT Committee focused heavily on long-term infrastructure planning during its...
Will County P&Z Logo Planning Zoning

Green Garden Solar Project Cleared to Implement Higher “Agrivoltaic” Standards

Will County Planning and Zoning Commission Meeting | May 5, 2026 Article Summary: The Will County Planning and Zoning Commission approved four variances on Tuesday, May 5, 2026, to facilitate...