(The Center Square) – As the country braces for a surge in electricity demand driven by large energy users like data centers, two questions lie at the center of the debate over the grid’s future: can it remain reliable and who will pay for it?

Utility experts warn that rising load forecasts are colliding with projected supply shortfalls. And, while PJM works to finalize new rules for connecting large load customers to the grid, some state officials, consumer advocates, and industry groups are zeroing in on the affordability piece of the puzzle.

Accurate load forecasting is essential in meeting rising demand without wasting capital on infrastructure that may never be used, and it affects everything – from keeping the lights on to the prices customers pay each month.

“Ghost projects” are a big part of the issues that are creating uncertainty, Todd Snitchler, president and CEO of the Electric Power Supply Association, or EPSA, told The Center Square.

A ghost project is a generation or transmission project that is announced or funded but never gets built.

Snitchler said gigawatts of new demand are being reported to the system, but there are duplications. Data center developers and hyperscalers routinely scout multiple locations at once, so the same potential project gets counted several times, artificially inflating the load forecast – leading to the risk of overbuilding, stranded costs, or unnecessary spending.

According to Snitchler, there are utilities pointing to these numbers to justify getting back into the business of rate-based generation, claiming they can deliver new plants faster and more cheaply, and with no impact on customers.

None of this can be true, he added, “because they’re subject to the same pressures we are as independent power producers.” And under their business model, they recover their costs plus a reasonable rate of return through a non-bypassable charge paid by customers.

Some states, he said, are tightening their tariffs to include only credible, large-load projects in forecasts. When AEP Ohio applied its new tariff, its projected growth over five years dropped from 30 GW to 13 GW – a 60% reduction. The former is equivalent to powering 26 million homes, while the latter is enough for 1.1 million.

“That suggests to me,” he said, “they can’t be alone in experiencing that.”

He noted that the load forecast for most Pennsylvania utilities was surprisingly flat, with others having only 1-1.5% annual growth, while PPL’s amounted to a 200% increase over 10 years. Something he says is wildly out of step with their peer utilities and raises questions about how thoroughly they are vetting projects, and how many are real.

He argued that overstated demand forecasts suggest developers need to build like crazy, justifying the utilities’ preference to get back into the rate-based generation business – and forcing customers to pay for new power plants instead of relying on the competitive market.

In these cases, Snitchler questions whether the projects are real, or simply advocacy tools designed to help publicly traded utilities grow their rate base and boost shareholder returns, as opposed to competitive developers who invest their own capital and bear the risk themselves.

His concern is that in addition to not having the best answer, there’s an incentive to have the wrong answer, because that helps advance policy objectives that may be better for some organizations, but are intentionally harmful to others.

The bottom line, EPSA says, is that realistic, data-driven planning ensures reliability for the 67 million customers in the PJM region. The solution to meeting demand is continued investment through competitive electricity markets in new and existing power generation, guided by disciplined, transparent forecasting that reflects the projects most likely to materialize.

“There is no silver bullet for this – and I’m not even convinced there’s silver buckshot. Because there’s so much happening that needs coordination for us to deliver and do our best, to ensure a reliable, affordable, and growing system,” Snitchler said. “I think everyone is aiming in the right direction, and we’d do a little better if we bickered less and cooperated more. But it doesn’t feel like where we are at the moment.”

“PJM is doing everything within our authority to reform our processes so they reflect load growth that is likely to occur, not just speculative activity,” Jeffrey Shields, PJM spokesperson, told The Center Square via email.

He said the potential for duplicative requests is one issue they are addressing with their stakeholders in the Critical Information Fast Path process for Large Load Additions, which will conclude on Nov. 19 with a recommendation to the PJM Board of Managers. The CIFP process was initiated by the Board in August to explore ways to continue to connect large loads to the system quickly and reliably without risking electricity shortages.

As part of the CIFP discussions, they are recommending several improvements to the load forecasting process, building on existing enhancements that incorporate large load adjustments into the long-term forecast. They have also standardized the system that load-serving entities use to request large load additions, to include evidence of binding commitments that facilities will be built.

PJM has also recommended a specific review process involving the states and utilities that operate within their borders; those states and their utilities also have authority to set rates and require commitments from data centers and other “large load” customers.

A summary of their proposal to deal with the issue will be considered along with 11 others.

Leave a Comment





Latest News Stories

Op-Ed: Your kids now belong to the Chicago Teachers Union

Op-Ed: Your kids now belong to the Chicago Teachers Union

By Mailee Smith | Illinois Policy InstituteThe Center Square Students who can’t read and secrecy from parents – that’s just part of the legacy of Stacy Davis Gates during her...
Illinois quick hits: Former police chief convicted of bribery; man sentenced for fraud

Illinois quick hits: Former police chief convicted of bribery; man sentenced for fraud

By Jim Talamonti | The Center SquareThe Center Square Former police chief convicted of bribery A federal jury has convicted a former Summit, Illinois police chief of bribery offenses for...

WATCH: Chicago mayor: ‘Wicked’ people want chaos; critics rip mayor

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – The mayor of Chicago has expressed his opposition to an alternative budget proposal from the city council....
WATCH: Chicago mayor warns of budget ‘chaos,’ end-of-life options bill on gov’s desk

WATCH: Chicago mayor warns of budget ‘chaos,’ end-of-life options bill on gov’s desk

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square Editor Greg Bishop provides highlights from...
Will County Board Land Use Committee Graphic.4

Committee Postpones Vote on Brandon Road Fill Operation After Tree Clearing Allegations

Will County Land Use & Development Committee Meeting | December 2025 Article Summary: The Will County Land Use and Development Committee voted to postpone a decision on a proposed clean...
Judy Ogalla

Ogalla Blasts New State Solar Legislation

Will County Land Use & Development Committee Meeting | December 2025 Article Summary: During a discussion on zoning matters, Will County Board Member Judy Ogalla strongly criticized the passage of...
Meeting Briefs

Meeting Summary and Briefs: Will County Planning and Zoning Commission for December 2, 2025

Will County Planning and Zoning Commission Meeting | December 2, 2025 Overall Meeting SummaryThe Will County Planning and Zoning Commission met on December 2, 2025, to consider a variety of...
Metra

Metra Announces No Fare Hikes; Highlights Bridge Projects in Joliet and Mokena

Will County Committee of the Whole Meeting | December 2025 Article Summary: Metra officials presented a balanced 2026 budget to the Will County Board, confirming that riders will not see...
Rent collusion suit tossed vs manufactured home community operators

Rent collusion suit tossed vs manufactured home community operators

By Scott Holland | Legal NewslineThe Center Square A federal judge has dismissed, for now, a class action accusing some of the nation’s largest manufactured home community landlords of rent...
Illinois quick hits: Planned vigil opposes physician-assisted suicide; NFIB urges veto of energy bill

Illinois quick hits: Planned vigil opposes physician-assisted suicide; NFIB urges veto of energy bill

By Jim Talamonti | The Center SquareThe Center Square Planned vigil opposes physician-assisted suicide A vigil is planned Thursday afternoon outside the State of Illinois building in Chicago’s West Loop,...
State rep: Pritzker already 'gamed the system' with redistricting

State rep: Pritzker already ‘gamed the system’ with redistricting

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Illinois Gov. J.B. Pritzker says Illinois lawmakers will take action if the Indiana legislature votes to redraw...

Public Works Committee: Will County Consolidates Paratransit Services Amid Funding Debates

Public Works & Transportation Committee Meeting | December 2, 2025 Article Summary: The Will County Board’s Public Works Committee advanced an agreement to consolidate paratransit services into a single countywide...
Blue Devil Logo Graphic

Peotone Rallies Past Reed-Custer in 38-36 Thriller

PEOTONE — In a game defined by defensive intensity and a second-half surge, the Peotone Blue Devils fought their way back from a halftime deficit to edge the Reed-Custer Comets, 38-36,...
Peotone High School

Peotone School Board Appoints Robert Steven Clark as New Board Member

Article Summary: The Peotone Board of Education approved the appointment of a new board member during a special meeting held on Monday evening. The board voted to seat Robert Steven...
Will County P&Z Logo Planning Zoning

P&Z Commission: Peotone Area Variances Forwarded for Garage and Pole Barn

Will County Planning and Zoning Commission Meeting | December 2, 2025 Article Summary: The Will County Planning and Zoning Commission approved variance requests for two properties in Peotone Township, allowing...