New Lenox Solar Farm Proposal Advances with Conditions, Following Village and Forest Preserve Input

Spread the love

Will County Planning and Zoning Commission Meeting | October 21, 2025

Article Summary: The Will County Planning and Zoning Commission recommended approval for a 62.7-acre commercial solar energy facility in New Lenox Township, contingent on several conditions, including the development of an emergency response plan and adherence to landscaping requests from the Village of New Lenox. The project, proposed by Nexamp Solar LLC, aims to contribute to Illinois’ renewable energy goals under the Climate and Equitable Jobs Act (CEJA).

Spencer Road Solar Farm Key Points:

  • Project Scope: A special use permit was sought for a commercial solar energy facility on a 110-acre property on South Spencer Road, utilizing approximately 62.7 acres for two projects totaling 5.25 MW (AC).

  • Variances Approved: The commission also recommended variances to allow pollinator-friendly ground cover to grow up to 36 inches (from 13 inches) and to reduce the required number of mowings from five to one annually.

  • Local Input: The Village of New Lenox did not object but recommended conditions concerning setbacks, access drive surfacing, fencing, and landscape screening. The Forest Preserve District of Will County also provided recommendations to protect local wildlife.

  • State Law Compliance: The project falls under Illinois Public Law 102-1123, which sets specific parameters and timelines for counties to review commercial solar energy proposals.

JOLIET, IL – The Will County Planning and Zoning Commission on Tuesday, October 21, 2025, recommended approval for a large-scale commercial solar energy facility on approximately 62.7 acres of agricultural land in New Lenox Township. The recommendation, which now goes to the full Will County Board for a final decision, includes a special use permit and two variances aimed at promoting pollinator-friendly habitats on the site.

The project, proposed by developer Nexamp Solar LLC under the names Spencer Road Solar East LLC and Spencer Road Solar West LLC, involves constructing two adjacent solar facilities on a 110-acre property located on South Spencer Road, south of the Village of New Lenox. The combined facilities will feature approximately 12,029 solar panels on single-axis tracker systems, generating a total of 5.25 megawatts (AC).

The proposal is part of the state’s Adjustable Block program under the Climate and Equitable Jobs Act (CEJA), which incentivizes renewable energy projects. According to Illinois law, county review of such projects is subject to a strict timeline, requiring a public hearing within 60 days of a complete application.

In addition to the special use permit, the commission recommended two variances from county code. The first increases the maximum allowed height for ground cover plants from 13 inches to 36 inches. The second reduces the required number of mowings from five times per year to just once. Staff reports indicated these variances are crucial for establishing a “pollinator-friendly solar site” under the Illinois Pollinator-Friendly Solar Site Act. The taller native vegetation and reduced mowing allow deep-rooted pollinator species to propagate, which helps recharge agricultural soils, improve water infiltration, and provide habitat for birds and insects.

The Village of New Lenox, whose corporate boundary is within 400 to 1,300 feet of the property, reviewed the project and did not object. However, the village board recommended five conditions for approval. These include meeting all county setback requirements, installing a concrete or asphalt surface for the access drive within the Spencer Road right-of-way, installing an eight-foot-tall Fixed Knot Farm fence, placing landscape screening along the western fence line, and abiding by all New Lenox Fire Protection District requirements.

The Forest Preserve District of Will County also submitted a letter with recommendations to mitigate environmental impacts. The district suggested installing wildlife-friendly fencing with a six-inch gap at the bottom to allow for animal movement, clearing trees only between November 1st and March 31st to protect wildlife, and using native quality plant species for landscaping.

According to the developer, the site will be remotely monitored 24/7, with employees only visiting occasionally for maintenance. The project is expected to create 20 to 25 local jobs during its estimated six-month construction phase, anticipated to begin in the fall of 2026. The developer has also entered into an Agricultural Impact Mitigation Agreement (AIMA) with the Illinois Department of Agriculture to ensure the preservation of the agricultural land and provide financial assurance for the eventual decommissioning of the facility.

Green Garden Weather Full forecast →
⚠️ Hydrologic Outlook issued June 16 at 2:13PM CDT by NWS Chicago IL
⚠️ Hydrologic Outlook issued June 16 at 2:12PM CDT by NWS Chicago IL
⚠️ Hydrologic Outlook issued June 16 at 2:44AM CDT by NWS Chicago IL
Today Jun 15
Slight Chance Showers And Thunderstorms
74° 54°

Slight Chance Showers And Thunderstorms

💨 20 to 25 mph 💧 21%

Leave a Comment





Latest News Stories

WATCH: National Guard case before SCOTUS; Trump insists China soybean deal coming

WATCH: National Guard case before SCOTUS; Trump insists China soybean deal coming

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square Editor Greg Bishop reviews the latest...
Screenshot 2025-10-17 at 11.31.38 AM

Lincoln-Way Board Honors Students with Perfect ACT Scores, Music Educator of the Year

LW210 Board of Education Meeting | October 16, 2025 Article Summary: Lincoln-Way District 210 celebrated exceptional academic and faculty achievement by formally recognizing nine students who earned a perfect composite...
Meeting Briefs

Meeting Summary and Briefs: Peotone Board of Education for September 29, 2025

Peotone School Board Special Board Meeting - Monday, September 29, 2025 The Peotone Board of Education held a special meeting on Monday, September 29, 2025, primarily to pass a revised...
Meeting-Briefs-4

Meeting Summary and Briefs: Green Garden Township for October 13, 2025

The Green Garden Township Board meeting on Monday, October 13, 2025, was dominated by two major issues: a growing community-led fight against a massive proposed solar facility and the board's...
Screenshot 2025-10-17 at 11.32.04 AM

Lincoln-Way Support Staff Union Rejects Tentative Contract Agreement

LW210 Board of Education Meeting | October 16, 2025 Article Summary: Members of the Lincoln-Way Community High School District 210 support staff union have voted down a tentative five-year contract...
Screenshot 2025-10-16 at 8.29.54 PM

Green Garden Abandons Town Hall Project, Forfeits Grant After County Shortens Deadline

Green Garden Township Meeting October 13 @ 7PM Article Summary: The Green Garden Township Board has officially withdrawn from a grant-funded project for a new town hall after Will County...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Legislative Committee for October 7, 2025

The Will County Legislative Committee held a long and contentious meeting on Tuesday, October 7, 2025, highlighted by the narrow 4-3 passage of a controversial resolution supporting protections for immigrant...
Screenshot 2025-10-17 at 11.13.13 AM

Peotone School Board Passes Revised Budget, Averting Financial Shutdown

Peotone School Board Special Board Meeting - Monday, September 29, 2025 Article Summary: Facing a state-mandated deadline, the Peotone Board of Education narrowly passed a revised 2025-2026 budget with a...
Screenshot 2025-10-16 at 8.30.46 PM

Green Garden Residents Mobilize Against Massive 18-Square-Mile Solar Facility

Green Garden Township Meeting October 13 @ 7PM Article Summary: A volunteer citizen group in Green Garden Township has announced a five-phase strategy to stop a massive commercial solar facility...
Meeting Briefs

Meeting Summary and Briefs: Peotone Board of Education for September 22, 2025

The Peotone school board on Monday, September 22, 2025, rejected the district's 2025-2026 budget, which carried a $4.2 million deficit, setting off an urgent scramble to find significant cuts before...
Screenshot 2025-10-10 at 12.05.55 PM

Will County Board Committee Passes Contentious ‘Live and Work Without Fear’ Resolution on 4-3 Vote

Will County Legislative Committee Meeting October 7, 2025 Article Summary: The Will County Legislative Committee on Tuesday narrowly passed a controversial resolution affirming the county's commitment to ensuring all residents...
Meeting Briefs

Will County Awards $10.4 Million Contract for Bell Road Widening in Homer Glen Area

Will County Public Works & Transportation Committee Meeting October 7, 2025 Article Summary: The Will County Public Works & Transportation Committee on Tuesday confirmed the award of a $10.4 million...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Finance Committee for October 7, 2025

The Will County Finance Committee on Tuesday, October 7, 2025, held a contentious meeting centered on the county’s finances, narrowly approving a preliminary $161.6 million county-wide tax levy on a...
Screenshot 2025-10-10 at 12.12.16 PM

Meeting Summary and Briefs: Will County Public Works & Transportation Committee for October 7, 2025

The Will County Public Works & Transportation Committee on Tuesday, October 7, 2025, approved a major construction contract and reviewed extensive plans for both county and state transportation initiatives. The...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Capital Improvements & IT Committee for October 7, 2025

The Will County Capital Improvements & IT Committee spent the bulk of its meeting on Tuesday, October 7, 2025, discussing the county’s long-term facilities master plan. Faced with an aging...