Land Use Committee: Monee Solar Projects Granted Extensions; Battery Storage Plans Dropped
Will County Land Use & Development Committee Meeting | December 2025
Article Summary: The Will County Land Use and Development Committee granted time extensions for two separate solar farm projects in Monee Township. During the review, it was revealed that the developer has removed the battery energy storage systems (BESS) from both applications, and Board Member Judy Ogalla clarified her stance on the projects based on their proximity to residential areas.
Monee Solar Extensions Key Points:
-
Project 1 (Monee Solar): Located at 26845 S. Will Center Road; extension approved 5-1.
-
Project 2 (Monee Solar West): Located at West Pauling Road and South Will Center Road; extension approved 6-0.
-
Major Change: The developer is no longer pursuing Battery Energy Storage Systems (BESS) at either location; the permits for those specific components will lapse.
-
New Deadline: Special use permits for the solar arrays are now valid through July 17, 2026.
The Will County Land Use and Development Committee on Thursday, Dec. 4, 2025, approved “first extensions” for two separate commercial solar energy facilities in Monee Township, giving the developers until July 2026 to obtain building permits.
The first project, Monee Solar, LLC, located at 26845 S. Will Center Road, was originally approved in January 2024. Staff reported that while the original approval included a special use permit for a Battery Energy Storage System (BESS), the applicant has decided not to move forward with the battery component. The extension request applies only to the solar farm itself.
Board Member Judy Ogalla voted against the extension for this specific site.
“I would not have supported this,” Ogalla said, referring to the original vote in early 2024. “That is way too close to residential… I would be a no on that.”
The committee voted 5-1 to approve the extension, with Ogalla voting no.
The second project, Monee Solar West, LLC, located at the northwest corner of West Pauling Road and South Will Center Road, also received an extension. Similar to the first project, the developer has dropped plans for a battery storage system at this site.
Ogalla voted in favor of this second extension, distinguishing it from the first project based on its location.
“The second one is not near residential, so I would be supporting that,” Ogalla noted.
The committee voted 6-0 to approve the extension for Monee Solar West. Both special use permits are now valid through July 17, 2026.
Latest News Stories
Chicago could owe $100M+ in refunds for excessive city tickets
Illinois quick hits: Indiana House approves Bears stadium bill; Business, labor groups file petition to stop natural gas phaseout; Chicago woman gets 2 years for PPP fraud
Community violence intervention advocates tout crime reduction, taxpayer funding
Pritzker’s social media fee plan faces cost, legality questions
Chicago tourism rises; visitors ignore Trump’s condemnation
Illinois quick hits: Chicago man faces charges in road-rage shooting; migrant accused of murdering church volunteer; Illinois Liquor Control Commission launches new system
Executive Committee Advances “Project Northwinds”: 2,475 Jobs and $346 Million Investment Proposed for Former Caterpillar, Lion Electric Sites
Land Use Committee Advances Mokena Scrap Yard and Homer Glen Landscape Business Over Local Objections
Foxx to face questions about murder conviction review ‘investigations’
Planning Commission Backs 5-MW Peotone Solar Farm; Developer Pledges Pollinator Habitat and Community Funds
207U Committee Reviews Budget Adjustments, Facility Planning and Operations Issues
Joliet Junior College Board Approves $2 Tuition Increase Amidst Heated Debate Over Enrollment and Spending
207U Board Outlines Long-Term Planning Timeline, Reviews Academic and District Updates
207U Board Tables Activity Bus Lease After Cost, Timing Concerns