Will County Landfill Committee Meeting | Jan. 13, 2026

Article Summary: The Landfill Committee voted to move forward with engineering estimates for a fourth compressor at the Prairie View Renewable Natural Gas (RNG) facility. The $1.8 million investment aims to reduce downtime and increase revenue, despite concerns about funding sources and timing.

RNG Plant Key Points:

  • Downtime Costs: Data shows that feed compressor failures account for nearly 36% of plant downtime, costing the county an estimated $600,000 annually in lost revenue.

  • Proposed Solution: Installing a fourth compressor would ensure three units are always operational, maximizing gas production and revenue. The estimated cost is $1.8 million with a 3-5 year return on investment.

  • Budget Concerns: The purchase was not included in the current fiscal year budget. Officials discussed using remaining funds from the previous year or splitting the cost across two budget cycles due to a 46-week lead time for the equipment.

Will County officials are taking steps to boost efficiency and revenue at the Prairie View Renewable Natural Gas (RNG) plant by pursuing the addition of a fourth feed compressor.

At the Landfill Committee meeting on Tuesday, January 13, 2026, Dave Hartke, Director of the Resource Recovery & Energy Division, presented data highlighting the financial impact of equipment failures. The facility’s three existing compressors are the primary cause of outages, leading to significant revenue losses.

“If we have three feed compressors operating at all times… we’re going to be producing closer to 27 to 2900 mm BTUs,” Hartke explained, noting this would allow the plant to hit higher revenue tiers faster each month.

The proposed fourth unit, estimated at $1.8 million fully installed, would provide redundancy. However, the plan faced scrutiny regarding its financing. Board Member Sherry Newquist questioned the timing, noting, “This kind of stuff is so much easier to deal with during the budget process.”

Hartke admitted the request was not in the original budget due to a prior focus on austerity. “I wasn’t quite expecting the response… that we should move forward with it,” he said, referencing earlier informal discussions with committee leadership.

Despite the budget hurdle, the committee saw the long-term value. With a 46-week lead time for the equipment, Finance Director Marcy indicated the cost could potentially be split across two fiscal years.

Board Member Jim Richmond emphasized the need for a deeper analysis before cutting a check. “This is a massive business decision… We need to actually look at that plant and make sure that it is spec’d properly from the front door to the back door,” Richmond said.

Ultimately, the committee voted unanimously to authorize staff to proceed with obtaining firm engineering costs and a project plan, which will then be brought back for final financial approval.

Leave a Comment





Latest News Stories

Ad-Hock-July-22nd

Will County Treasurer Confirms Free Online Tax Payment Option, Warns Against High Credit Card Fees

Will County Treasurer Tim Brophy confirmed Tuesday that property owners have a free online payment option available and advised residents to avoid the high convenience fees associated with using credit...
Ad-Hock-July-22nd

Committee Highlights ‘Lack of Teeth’ in County Code Enforcement Process

While the Will County Ad-Hoc Ordinance Review Committee quickly approved minor updates to its administrative adjudication ordinance Tuesday, the action sparked a broader discussion about resident frustration over the enforcement...
Ad-Hock-July-22nd

Committee Highlights ‘Lack of Teeth’ in County Code Enforcement Process

While the Will County Ad-Hoc Ordinance Review Committee quickly approved minor updates to its administrative adjudication ordinance Tuesday, the action sparked a broader discussion about resident frustration over the enforcement...
Meeting-Briefs

Meeting Briefs: Will County Ad-Hoc Ordinance Review Committee for July 22, 2025

AI Policy Discussion Urged: Chair Jackie Triner called for the county to develop a comprehensive policy on the use of Artificial Intelligence. Citing a recent conference, Triner noted the potential benefits...
Peotone-Special-Board-Meeting-July-21

Peotone School Board Approves Sweeping Personnel Changes, Fills Key Vacancies

The Peotone School District 207-U Board of Education approved a lengthy and significant personnel report during a special meeting on Monday, July 21, addressing numerous vacancies through new hires, internal...
Peotone-Special-Board-Meeting-July-21.2

Resident Alleges Financial Mismanagement, Underused Buildings at Peotone Board Meeting

A Peotone resident and village trustee, Jim Bowden, confronted the Peotone School District 207-U Board of Education during its special meeting Monday with a series of sharp allegations regarding building...
Meeting-Briefs

Meeting Briefs: Peotone School District 207-U for July 21, 2025

PES Pickup Route Scrutinized: Resident Kacey Dewall revisited concerns about the parent pickup route for Peotone Elementary School on Oak Street, citing ongoing issues with blocked driveways and mail delivery. District...
WCO-PZ-July-15

Crete Township Wins Approval for New Digital Sign at Community Center

Crete Township received approval from the Will County Planning and Zoning Commission on Tuesday for a new digital sign at its community center, a project that required a special use...
WCO-PZ-July-15

Will County Planners OK Oversized Garage Near Naperville, Overriding Staff Recommendation

The Will County Planning and Zoning Commission on Tuesday approved variances for a new oversized accessory garage in Wheatland Township, siding with a homeowner and builder over a staff recommendation...
WCO-PZ-July-15

Green Garden Landscaping Business Gains Permit Amid Strong Neighbor Support

A small landscaping and lawn maintenance business operating on a residential property in Green Garden Township received official approval Tuesday after neighbors voiced overwhelming support for the operation. The Will...
Meeting-Briefs

Meeting Briefs: Will County Planning and Zoning Commission for July 15, 2025

Frankfort Shed Relocation Approved: A homeowner on West Harvest Drive in Frankfort Township received a variance to reduce an east side-yard setback from 10 to 4 feet. The variance, sought by...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves ‘Whisk & Flame’ Culinary Studio, Slashes Parking Requirement for Downtown Property

An experiential culinary studio named Whisk & Flame is set to open in downtown Frankfort after the Village Board approved a series of special use permits and a significant parking...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Village Board Adopts $59.4 Million Appropriation for Fiscal Year 2026

The Frankfort Village Board has formally set its maximum legal spending limit for the upcoming fiscal year, adopting a $59,366,900 appropriation ordinance for fiscal year 2026. The measure was passed...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Establishes New Zoning Rules to Attract Data Centers

The Village of Frankfort has amended its zoning ordinance to create a specific use category for data centers, a move designed to regulate and attract high-tech development. The Village Board...
Frankfort-Village-Board-Meeting-Graphic

Currie Motors Expansion Gets Approval with Site Modifications

Currie Motors on Lincoln Highway received approval from the Frankfort Village Board on Monday for a major change to its site plan, allowing for the construction of seven new parking...