Will County Board Graphic.03

Landfill Committee Advances Plan to Purchase Fourth Compressor for RNG Plant

Spread the love

Will County Landfill Committee Meeting | Jan. 13, 2026

Article Summary: The Landfill Committee voted to move forward with engineering estimates for a fourth compressor at the Prairie View Renewable Natural Gas (RNG) facility. The $1.8 million investment aims to reduce downtime and increase revenue, despite concerns about funding sources and timing.

RNG Plant Key Points:

  • Downtime Costs: Data shows that feed compressor failures account for nearly 36% of plant downtime, costing the county an estimated $600,000 annually in lost revenue.

  • Proposed Solution: Installing a fourth compressor would ensure three units are always operational, maximizing gas production and revenue. The estimated cost is $1.8 million with a 3-5 year return on investment.

  • Budget Concerns: The purchase was not included in the current fiscal year budget. Officials discussed using remaining funds from the previous year or splitting the cost across two budget cycles due to a 46-week lead time for the equipment.

Will County officials are taking steps to boost efficiency and revenue at the Prairie View Renewable Natural Gas (RNG) plant by pursuing the addition of a fourth feed compressor.

At the Landfill Committee meeting on Tuesday, January 13, 2026, Dave Hartke, Director of the Resource Recovery & Energy Division, presented data highlighting the financial impact of equipment failures. The facility’s three existing compressors are the primary cause of outages, leading to significant revenue losses.

“If we have three feed compressors operating at all times… we’re going to be producing closer to 27 to 2900 mm BTUs,” Hartke explained, noting this would allow the plant to hit higher revenue tiers faster each month.

The proposed fourth unit, estimated at $1.8 million fully installed, would provide redundancy. However, the plan faced scrutiny regarding its financing. Board Member Sherry Newquist questioned the timing, noting, “This kind of stuff is so much easier to deal with during the budget process.”

Hartke admitted the request was not in the original budget due to a prior focus on austerity. “I wasn’t quite expecting the response… that we should move forward with it,” he said, referencing earlier informal discussions with committee leadership.

Despite the budget hurdle, the committee saw the long-term value. With a 46-week lead time for the equipment, Finance Director Marcy indicated the cost could potentially be split across two fiscal years.

Board Member Jim Richmond emphasized the need for a deeper analysis before cutting a check. “This is a massive business decision… We need to actually look at that plant and make sure that it is spec’d properly from the front door to the back door,” Richmond said.

Ultimately, the committee voted unanimously to authorize staff to proceed with obtaining firm engineering costs and a project plan, which will then be brought back for final financial approval.

Leave a Comment





Latest News Stories

Frankfort-Township-Logo-Graphic

Meeting Briefs: Frankfort Township Board for April 14, 2025

The Frankfort Township Board of Trustees met on Monday, April 14, 2025, to address zoning matters and new business. The board took a firm stance against government consolidation, unanimously passing...
Green-Garden-Logo.WP

Comprehensive Plan Update Proceeds Despite Request from Incoming Officials

GREEN GARDEN TOWNSHIP — The Green Garden Township Planning Commission is moving forward with updating the township's comprehensive plan despite renewed requests from incoming elected officials to put the project...
Green-Garden-Logo.WP

Township Sees Significant Growth as Assessor Reports 39 New Home Construction Sites

GREEN GARDEN TOWNSHIP — Green Garden Township is experiencing substantial residential growth with 39 new home construction sites currently underway, according to a report delivered by Township Assessor Bushong at...
Green-Garden-Logo.WP

Township Trustee Defends Building Renovation Project, Addresses Parking Concerns

GREEN GARDEN TOWNSHIP — Trustee Wagner provided information about the township's building renovation project at the February meeting, responding to concerns raised at the previous month's session and clarifying several...
Green-Garden-Logo.WP

Green Garden Township News Briefs – February 2025

Speed Limit Reduced on 88th Avenue: Road Commissioner Hilliard reported that following a speed study, the Will County Board has voted to reduce the speed limit on 88th Avenue from...
MFPD-Logo-Fire-District-8

Fire District Receives Clean Audit, Adds 9 New Firefighters Despite Staff Departures

The Manhattan Fire Protection District received a clean audit report for fiscal year 2023 while addressing staffing challenges with nine new part-time firefighters set to join the department at the...
Peotone-High-School-scaled-3

Parents Allege Major PowerSchool Breach, Bullying Ignored by Peotone School Officials

The Peotone School Board faced a series of sharp criticisms Monday night from parents and community members who described a culture where bullying persists, communication is lacking, and a significant...
MFPD-Logo-Fire-District-9

Construction Manager Decision Delayed for New Fire Station Project

The Manhattan Fire Protection District has postponed a decision on hiring a construction management company for its new fire station project while fee structures are finalized. Board members met with...
Peotone-School-District

Peotone Board Celebrates Student Achievements in Academics and Athletics

The Peotone School Board celebrated a wide range of student accomplishments, from academic honors to major athletic milestones. The "Good News" portion of the meeting highlighted several students for their...
MFPD-Logo-Fire-District-10

Manhattan Fire District March 17 Meeting Briefs

Vehicle Updates Progressing: The new Tahoe ordered last year has arrived but will require several months before entering service. The ambulance damaged in December's crash is currently at the body...
Peotone-Junior-High-School-scaled-3

Peotone School Board Briefs

Two Administrators ResignPeotone High School will be seeking a new assistant principal and Peotone Elementary School a new principal following the board's acceptance of two administrative resignations Monday night. The...
Green-Garden-Logo.WP

Green Garden Board Approves Comprehensive Plan Update Despite Opposition

GREEN GARDEN TOWNSHIP — The Green Garden Township Board voted 3-2 to approve a $24,885 contract for updating the township's comprehensive plan during a contentious January meeting, despite requests from...
Green-Garden-Logo.WP

Township Building Renovation Sparks Debate

GREEN GARDEN TOWNSHIP — The current Green Garden Township Hall's future and a planned renovation project became focal points of debate at January's board meeting, with residents and officials offering...
Green-Garden-Logo.WP

Green Garden Township News Briefs

Assessor Outlines Tax Assessment Timeline: Assessor Bushong reported township-level assessments will open January 21, 2025, and close June 13, 2025. She explained the timing issue with the budget approval in...
MFPD-Logo-Fire-District-5

Manhattan Fire District Advances New Station Construction, Approves $210,000 Ambulance Replacement

The Manhattan Fire Protection District is moving closer to breaking ground on its new fire station, with construction documents expected to be complete next month and a potential groundbreaking scheduled...