Article Summary: The Executive Committee approved an agreement with BNSF Railway to construct a grade separation bridge on Lorenzo Road in Wilmington. The railroad will contribute over $15 million toward the project and provide a one-time maintenance payment to the county.

Lorenzo Road Bridge Key Points:

  • Project: Construction of a grade separation bridge carrying Lorenzo Road (CH 80) over the BNSF Railroad tracks.

  • Location: 1.25 miles west of I-55 in County Board District 1.

  • Total Cost: The estimated total project cost is $28,717,523.80.

  • Railroad Contribution: BNSF will reimburse the county 100% of costs after the execution of ICC funds, up to a cap of $15,102,943.80.

  • Maintenance Fee: BNSF will pay Will County a one-time maintenance fee of $675,003.28 for the useful life of the overpass.

The Will County Board Executive Committee on Wednesday, February 11, 2026, approved Resolution 26-046, authorizing an agreement between the County and BNSF Railway for a major infrastructure project on Lorenzo Road.

The project involves constructing a bridge to separate the grade of Lorenzo Road (County Highway 80) from the BNSF rail line, located approximately 1.25 miles west of Interstate 55. The project aims to eliminate the at-grade crossing, improving safety and traffic flow in the heavy industrial corridor.

According to the agreement attached to the agenda, the total estimated cost of construction is $28,717,523.80. Under the terms of the deal, BNSF Railway will contribute significantly to the project. Once $12 million in Illinois Commerce Commission (ICC) funds are executed, BNSF will reimburse the county for remaining costs up to a cap of $15,102,943.80.

Additionally, the agreement stipulates that BNSF will provide a one-time lump sum payment of $675,003.28 to the county to cover future maintenance costs for the structure over its useful life. The county will be responsible for maintaining the roadway, bridge structure, and drainage.

The agreement requires the contractor to maintain strict safety clearances during construction, including 25 feet horizontally from the track centerline.

The measure was moved by Member Jacqueline Traynere and seconded by Member Denise Winfrey. It passed unanimously.

Leave a Comment





Latest News Stories

Will County P&Z Logo Planning Zoning.2

P&Z Commission Approves Side Yard Setback Variance for Joliet Detached Garage

Will County Planning and Zoning Commission Meeting | March 3, 2026 Article Summary: The Will County Planning and Zoning Commission approved a variance to reduce a side yard setback on...
Will County Finance Logo

Will County Closes Out $16.2 Million Federal Rental Assistance Program, Transitions to Local Funding

Will County Finance Committee Meeting | March 3, 2026 Article Summary: Will County has officially closed out its massive federal Emergency Rental Assistance program after distributing millions to keep nearly 2,000...
Will County Board Graphic.01

Executive Committee Advances Sweeping Overhaul of Will County Business Regulations

Will County Executive Committee Meeting | March 12, 2026 Article Summary: Will County is poised to modernize its business regulations following the Executive Committee's unanimous approval of a massive ordinance overhaul....
will county Committee-Capital Improvement.Graphic

Will County Leaders Debate New Construction to Escape $1.2 Million in Leases

Capital Improvements & IT Committee Meeting | March 2026 Article Summary: The Will County Capital Improvements and IT Committee is aggressively exploring options to consolidate county offices and exit leased...
Will County P&Z Logo Planning Zoning

Meeting Summary and Briefs: Will County Planning and Zoning Commission for March 3, 2026

Will County Planning and Zoning Commission Meeting | March 3, 2026 Overall Meeting SummaryThe Will County Planning and Zoning Commission convened on Tuesday, March 3, 2026, to review a series...
Peotone School District 207U Committee of the Whole meeting March 16, 2026

Peotone 207U Weighs School Consolidation, Long-Term Planning in Lengthy Committee Meeting

By Andrea Arens The Peotone 207U Committee of the Whole spent several hours on March 16 discussing school consolidation plans, facility planning, and long-term financial strategy, with board members signaling...
Will County Finance Logo

Meeting Summary and Briefs: Will County Finance Committee for March 3, 2026

Will County Finance Committee Meeting | March 3, 2026 The Will County Board Finance Committee met on Tuesday to review a slate of year-end financial reports and approve routine budget...
Will County Finance Logo

Opioid Settlement Grants Funnel Nearly $600,000 to Local Police and Community Programs

Will County Finance Committee Meeting | March 3, 2026 Article Summary: Will County is distributing a significant portion of its opioid settlement funds to hyper-local agencies, including the Peotone and Manhattan...
Peotone softball blue devil graphic

Plainfield Central Offense Surges in 14-4 Victory Over Peotone Softball

The Peotone varsity softball team opened its 2026 campaign on the road Saturday morning, dropping a 14-4 non-conference decision to Plainfield Central. Despite getting on the board and pushing four...
Committee-Ad-Hoc.Graphic

Meeting Summary and Briefs: Will County Board Ad-Hoc Ordinance Review Committee for March 10, 2026

Will County Board Ad-Hoc Ordinance Review Committee Meeting | March 10, 2026 The Will County Board Ad-Hoc Ordinance Review Committee met on Tuesday, March 10, 2026, to review a backlog...
Peotone 207U School Board meeting March 16, 2026.

Peotone 207U Board Confronts Budget Pressures, Facility Needs at March 16 Meeting

By Andrea Arens Financial uncertainty, facility limitations, and growing calls for a community referendum dominated discussion at the Peotone Community Unit School District 207U Board of Education meeting on March...
Will County Board Graphic.02

Ad-Hoc Committee: Will County Sheriff’s Office to Acquire Decibel Meters for Noise Complaints

Will County Board Ad-Hoc Ordinance Review Committee Meeting | March 10, 2026 Article Summary: The Will County Sheriff's Office plans to purchase a fleet of certified decibel meters to accurately...
Will County P&Z Logo Planning Zoning

Crest Hill Homeowner Granted Side Yard Setback Variance for Accessible Addition

Will County Planning and Zoning Commission Meeting | March 3, 2026 Article Summary: The Will County Planning and Zoning Commission approved a side yard setback variance for a Crest Hill...
Will County Public Works Committee

Will County Public Works Approves Access for 56-Acre Truck Services Hub on Manhattan-Monee Road

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Will County Public Works and Transportation Committee on Tuesday approved a request to allow commercial ingress...
Will County Public Works Committee

Committee Approves $317K Guardrail Maintenance Contract Amid Discussion on Installation Dangers

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: Will County officials approved an annual guardrail maintenance contract Tuesday while addressing national concerns over improperly installed...