Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Leave a Comment





Latest News Stories

MFPD-Logo-Fire-District-3

Fire District Approves Construction Manager for New Station, Targets May 5 Bid Opening

The Manhattan Fire Protection District selected ICI Build as its construction management company for the new fire station project and is targeting May 5 for opening construction bids. The board...
MFPD-Logo-Fire-District-15

Fire District Approves Construction Manager for New Station, Targets May 5 Bid Opening

The Manhattan Fire Protection District selected ICI Build as its construction management company for the new fire station project and is targeting May 5 for opening construction bids. The board...
MFPD-Logo-Fire-District-19

Fire District Expands Health Programs, Considers Cancer Screening

The Manhattan Fire Protection District is expanding its employee wellness initiatives with potential cancer screening through body scans and continuing its successful injury prevention program. The Health and Safety Committee...
MFPD-Logo-Fire-District-4

Fire District Expands Health Programs, Considers Cancer Screening

The Manhattan Fire Protection District is expanding its employee wellness initiatives with potential cancer screening through body scans and continuing its successful injury prevention program. The Health and Safety Committee...
MFPD-Logo-Fire-District-11

Fire District May 21 Meeting Briefs

Policy Manual Nearly Complete: The district's operational procedures and policy manual is 95% complete, with attorney review and union input ongoing. The complete manual will be presented to the board...
default

Lincoln-Way Board Approves Up to $31.3 Million Bond Sale for Safety, Security Upgrades

The Lincoln-Way Community High School District 210 Board of Education unanimously approved a resolution to issue up to $31.33 million in life safety bonds to fund a wide range of...
frankfort-square-park-district.2

Frankfort Square Park District Approves Budget Amid County Tax Adjustment, Funds Major Projects

The Frankfort Square Park District Board of Commissioners unanimously approved its operating budget for the 2025-2026 fiscal year during its April 17 meeting, earmarking funds for major ongoing projects and...
default

Lincoln-Way School Board Certifies Election, Re-elects Janik as President

The Lincoln-Way Community High School District 210 Board of Education officially reorganized for the upcoming year during its meeting on April 17, certifying the results of the April 1 consolidated...
lincoln-way-school-district.3-scaled-e1750128024313

New Electricity Contract to Save Lincoln-Way Over $500,000 Next Year

Lincoln-Way High School District 210 is poised for significant energy cost savings after the Board of Education unanimously approved a new 54-month electric commodity contract with Direct Energy. The agreement,...
frankfort-square-park-district.1

Four New Commissioners to Join Frankfort Square Park District Board in May

Four newly elected commissioners are set to join the Frankfort Square Park District Board in May, following the April 1, 2025, Consolidated Election. Executive Director Audrey Marcquenski formally congratulated Lauren...
Meeting-Briefs

Meeting Briefs: Frankfort Square Park District for April 17, 2025

The Frankfort Square Park District Board of Commissioners met on April 17 to approve its annual budget, discuss new projects, and hear departmental updates. The district approved a nearly $5...
lincoln-way-school-district.3-scaled-e1750128024313

Lincoln-Way District 210 Board Briefs

District Finances Stable in March ReportAssistant Superintendent Michael Duback presented the Treasurer’s Report for the month ending March 31, 2025. Revenues for the month totaled $3.1 million, while expenditures were...
Frankfort-Township-Logo-Graphic

Frankfort Township Board Unanimously Opposes Government Consolidation

The Frankfort Township Board on Monday took a firm stance against a perennial issue in Illinois politics, unanimously passing a resolution to formally oppose any legislative efforts to consolidate or...
Frankfort-Township-Logo-Graphic

Frankfort Township Upgrading Senior Apartments Amidst High Demand

Frankfort Township is moving forward with significant upgrades to its senior apartments to meet modern standards, Supervisor Nick George announced at Monday’s board meeting. The improvements come as the township...
Frankfort-Township-Logo-Graphic

Outdoor Bar Expansion Gets Green Light from Frankfort Township

The Frankfort Township Board has approved a special use permit that will allow a bar in an unincorporated area to expand its service outdoors. The unanimous decision was made during...