Will County Board Graphic.03

Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Spread the love

Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Leave a Comment





Latest News Stories

Illinois Quick Hits: Pritzker blasts Trump military action

Illinois Quick Hits: Pritzker blasts Trump military action

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Illinois Gov. J.B. Pritzker says President Donald Trump is once again sidestepping the Constitution and failing to...
Plastics industry applauds Trump's focus on strengthening manufacturing

Plastics industry applauds Trump’s focus on strengthening manufacturing

By Tate MillerThe Center Square The plastics industry is pleased by President Donald Trump’s mention at the State of the Union of strengthening manufacturing in the nation, with an industry...
Committee-Land Use.Graphic

Meeting Summary and Briefs: Will County Land Use & Development Committee for February 5, 2026

Will County Land Use & Development Committee Meeting | February 5, 2026 The Will County Land Use and Development Committee met on Thursday, February 5, 2026, to deliberate on several...
Screenshot 2026-02-22 at 5.06.42 PM

Meeting Summary and Briefs: Joliet Junior College Board of Trustees for February 18, 2026

Joliet Junior College Board of Trustees Meeting | February 18, 2026 Meeting SummaryThe Joliet Junior College Board of Trustees met on Wednesday, February 18, 2026, for a regular meeting dominated...
Committee-Executive.Graphic

Meeting Summary and Briefs: Will County Executive Committee for February 11, 2026

Will County Executive Committee Meeting | February 11, 2026 Meeting SummaryThe Will County Board Executive Committee met on Wednesday, February 11, 2026, tackling a heavy agenda focused on economic development...
Election Vote Graphic

Group Presents Allegations of 2024 Voter Roll Errors to County Board

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board approved a resolution calling for the review of election systems and integrity, following public comments alleging inaccuracies...
Trump: Iran operations to continue until objectives achieved

Trump: Iran operations to continue until objectives achieved

By Sarah Roderick-FitchThe Center Square Combat operations will continue in Iran at “full force” until American “objectives are achieved,” President Donald Trump said during his second address to the nation...

Everyday Economics: The Fed’s labor-market reality check

By Orphe DivounguyThe Center Square Last week wasn’t about a single data point. It was about a shift in tone from policymakers: the labor market may be weaker than the...
Trump: Nine Iranian ships destroyed; Iran wants to talk

Trump: Nine Iranian ships destroyed; Iran wants to talk

By Sarah Roderick-FitchThe Center Square Nine Iranian ships have been “destroyed and sunk” by U.S. forces as part of Operation Epic Fury, according to President Donald Trump. The president’s announcement...
Supreme Court to hear gun possession for drug users case

Supreme Court to hear gun possession for drug users case

By Andrew RiceThe Center Square The U.S. Supreme Court will hear arguments on Monday in a consequential case over whether regular drug users can possess firearms. The case, U.S. v....
CENTCOM quashes Iranian claims of missile strikes on Lincoln

CENTCOM quashes Iranian claims of missile strikes on Lincoln

By Sarah Roderick-FitchThe Center Square U.S. Central Command is calling claims by the Islamic Revolutionary Guard that it struck the USS Abraham Lincoln a “lie.” The IRGC said that it...
CENTCOM: Three U.S. service members killed; first casualties of Operation Epic Fury

CENTCOM: Three U.S. service members killed; first casualties of Operation Epic Fury

By Sarah Roderick-FitchThe Center Square Three U.S. service members have been killed in action by Iranian strikes as part of Operation Epic Fury, according to U.S. Central Command. In addition...
Ahead of Iran strikes, CBP, DOJ taking action against Iranian influence in US

Ahead of Iran strikes, CBP, DOJ taking action against Iranian influence in US

By Bethany BlankleyThe Center Square Ahead of the U.S. strikes against Iranian leaders on Saturday, federal agents had already been addressing Iranian threats in the U.S. and on the high...
Will County Board Graphic.04

Will County Board Advised on Strict “Judicial” Role Ahead of Landfill Expansion Application

Will County Landfill Committee Meeting | February 10, 2026 Article Summary: During a detailed legal briefing on Tuesday, the Will County Landfill Committee received strict instructions regarding their conduct during...
Committee-Ad-Hoc.Graphic

Ad-Hoc Committee: Bath House Regulations Updated; Removes 60-Day Licensing Window

Will County Ad-Hoc Ordinance Review Committee Meeting | February 10, 2026 Article Summary: The Will County Board Ad-Hoc Ordinance Review Committee approved updates to the regulations governing bath houses and...