Will County Public Works Committee

Public Works Committee: Approves $1.59 Million Contract for Scheer Road Bridge Replacement in Green Garden Township

Spread the love

Will County Public Works and Transportation Committee Meeting | March 3, 2026

Article Summary: The Will County Public Works and Transportation Committee on Tuesday advanced a nearly $1.6 million contract to “D” Construction for a complete bridge replacement over Forked Creek.

Scheer Road Bridge Key Points:

  • The $1,596,116.16 contract was awarded to Coal City-based “D” Construction, Inc.

  • The project involves the removal of the existing bridge and construction of a new single-span concrete beam bridge.

  • The work on Scheer Road over Forked Creek is located in Green Garden Township (County Board Districts 2 and 3).

  • Construction will require a full roadway closure from April through September 2026.

The Will County Public Works and Transportation Committee on Tuesday, March 3, unanimously confirmed the award of a massive infrastructure contract to replace the aging Scheer Road bridge in Green Garden Township.

The $1,596,116.16 contract was awarded to “D” Construction, Inc., out of Coal City, which submitted the lowest qualified bid during the February 18 letting. The project will be funded through a combination of the Road District’s allotment of Motor Fuel Tax (MFT) funds and County Bridge Tax funds.

The comprehensive project (Section 21-07104-02-BR) will take place on Scheer Road over Forked Creek, impacting County Board Districts 2 and 3.

According to the project summary provided in the agenda packet, the scope of work consists of the complete removal of the existing bridge structure. In its place, crews will construct a new single-span concrete beam bridge. The project also entails installing new full-depth hot-mix asphalt pavement approaching the bridge, reconstructing the aggregate approach chip and seal north of the bridge, and adding new aggregate shoulders, guardrails, and riprap.

The road will be completely closed during the construction period. Work is estimated to begin in April 2026, with an estimated completion date of September 25, 2026.

The committee passed the resolution confirming the award without opposition.

Leave a Comment





Latest News Stories

Defense says more time needed for Tyler Robinson case

Defense says more time needed for Tyler Robinson case

By Dave MasonThe Center Square The defense won’t waive its right to a preliminary hearing but needs more time before a date is set, the court-appointed attorney for Tyler James...
Tribal members want 15 minutes for oral arguments in tariff case

Tribal members want 15 minutes for oral arguments in tariff case

By Brett RowlandThe Center Square Blackfeet Nation members asked the Supreme Court on Monday to set aside 15 minutes during oral arguments in the case challenging President Donald Trump's tariffs....
Welfare reform pilot to reduce government dependency is ‘step forward’, scholar says

Welfare reform pilot to reduce government dependency is ‘step forward’, scholar says

By Tate MillerThe Center Square (The Center Square ) – A Cato scholar called the Department of Health and Human Service’s redesigned welfare pilot that intends to reduce government dependency...
Illinois quick hits: Pritzker monitoring federal deployments; IDOT discusses Chicago to Rockford plans

Illinois quick hits: Pritzker monitoring federal deployments; IDOT discusses Chicago to Rockford plans

By Jim Talamonti | The Center SquareThe Center Square Pritzker monitoring federal deployments Gov. J.B. Pritzker says he is closely monitoring federal deployments in the Chicago suburb of Broadview. Protesters...
WATCH: Homeland Security arrests ICE protesters with guns; Bailey seeks Pritzker rematch

WATCH: Homeland Security arrests ICE protesters with guns; Bailey seeks Pritzker rematch

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square Editor Greg Bishop unpacks some of...
lincoln way school district 210 logo.2

Lincoln-Way Board Weighs Community Solar Program Promising $155,000 in Annual Savings

Article Summary: The Lincoln-Way District 210 board is considering a 20-year agreement to participate in a state-sponsored community solar program that could save the district an estimated $155,000 annually on electricity...
WCO 2025-09-27 at 9.04.56 AM

Will County Reverses Zoning on Peotone Farmland to Facilitate 10-Acre Sale

Article Summary: The Will County Board unanimously approved a request to rezone a 10.08-acre portion of a property in Will Township back to agricultural use, reversing a 2023 zoning change....
Meeting Briefs

Meeting Summary and Briefs: Joliet Junior College Board of Trustees for September 10, 2025

Joliet Junior College Board of Trustees Meeting | September 2025 The Joliet Junior College (JJC) Board of Trustees approved a landmark agreement with the City of Joliet to explore a...
Screenshot

Lincoln-Way 210 Board Approves $172.7 Million Budget with Planned Deficit for Bus Purchases

Article Summary: The Lincoln-Way Community High School District 210 Board of Education approved the Fiscal Year 2026 budget, which includes a planned operating deficit of $814,000 to accommodate the purchase of...
Lawmakers push for transit reform, funding despite delayed fiscal cliff

Lawmakers push for transit reform, funding despite delayed fiscal cliff

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Illinois lawmakers say they hope to pass transit legislation during the fall veto session next month, even...
Miller files ‘parental rights’ constitutional amendment, blasts Illinois’ policies

Miller files ‘parental rights’ constitutional amendment, blasts Illinois’ policies

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – Illinois U.S. Rep. Mary Miller says parental rights are being diminished and it’s time they speak up....
Enbridge Energy

Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements

Article Summary: Will County will reimburse Enbridge Energy for costs associated with relocating its pipeline facilities to make way for roadway improvements on Exchange Street in the Monee and Crete...
diamond shaped orange red reflector street sign that reads road

Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign

Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for...
solar panels photovoltaics in solar farm

“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension

Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited "ongoing uncertainty regarding federal...
solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy...