will county Committee-Capital Improvement.Graphic

Will County Leaders Debate New Construction to Escape $1.2 Million in Leases

Spread the love

Capital Improvements & IT Committee Meeting | March 2026

Article Summary: The Will County Capital Improvements and IT Committee is aggressively exploring options to consolidate county offices and exit leased properties, sparking a debate over where to build a new government campus and how to fund it.

Capital Improvements 5-Year Plan Key Points:

  • Will County currently utilizes approximately 65,000 square feet of leased space, costing taxpayers roughly $1.2 million annually.

  • A Master Plan Update in the agenda packet projects the county will need 118,000 square feet for the County Office Building and 101,040 square feet for Judicial Agencies by 2050.

  • Committee members are divided on whether to build a new facility on the site of the recently demolished old courthouse or expand the current county office campus.

  • A debt capacity report indicates the county could potentially issue up to $142.6 million in new bonds without increasing the overall annual debt service level.

The Will County Capital Improvements and IT Committee on Tuesday, March 3, 2026, waded into a complex debate over the future of the county’s physical footprint, driven by a desire to consolidate scattered departments and eliminate expensive rental leases.

Committee Chair Mica Freeman initiated the discussion by outlining her vision to bring currently displaced departments—such as the Public Defender, State’s Attorney, and Regional Office of Education—under a single, county-owned roof.

According to County Board Member Daniel J. Butler, the county’s reliance on leased spaces is currently a significant financial drain.

“We use 65,000 square feet of rental space and we paid $1.2 million for rental,” Butler said, noting that these costs were part of the original argument for attempting to save and expand the old 140,000-square-foot county courthouse before the board ultimately voted to demolish it.

“Building a new courthouse building in that exact same location would be the height of folly. I mean, really, tearing down the building and building it right back,” Butler remarked, though he acknowledged the urgent need to address the spatial deficit.

Member Steve Balich argued that the most logical and cost-effective long-term solution is to construct a new, basic facility—potentially on the site of the old courthouse—to eliminate the rental overhead.

“You just build a two-story building, steel, it’s cheaper, and move everybody in there, move everybody into different places in the building, and we’ll save a ton of money in rental,” Balich said. “We don’t really need to have bonds because we’ll be able to take the rent money to pay for the cost of a building.”

However, Member Jacqueline Traynere strongly opposed any plan that might increase the tax burden, and pushed back against utilizing the old courthouse site due to historical construction hurdles.

“I’m not in favor of raising property taxes to pay for new buildings,” Traynere said. She advocated for constructing a smaller, expandable building on the current County Office Building campus instead. “We could put parking at the bottom of the building, but we can’t go down deep because that’s limestone. That was the problem we had with the jail. Building anywhere in that general vicinity costs us a lot of extra money.”

While the committee did not take a formal vote, the agenda packet included deep contextual data to inform their upcoming decisions. A Master Plan Update provided by Wight projects that by the year 2050, the County Office Building departments will require 118,000 Departmental Gross Square Feet (DGSF), up from their current 62,260 DGSF. Similarly, Judicial Agency Departments will see their needs grow from 88,841 DGSF to 101,040 DGSF.

To finance potential construction, the committee referenced a recent debt profile from Speer Financial, included in the packet. The report shows that as older bonds are paid off, Will County will experience a significant drop in outstanding debt payments after 2026 and 2030. By structuring a split-issuance of General Obligation Alternate Revenue Source bonds, the county could theoretically capture up to $142.6 million in project funds without raising its current $25 million annual debt service target.

Member Mark V. Revis suggested that once staff returns with concrete price-per-square-foot estimates, the board should convene a special meeting to ensure all members are aligned before moving forward.

“This is one of those items that is going to cross the threshold where everybody is going to want to have a firm understanding of it before they cast their vote,” Revis said.

Leave a Comment





Latest News Stories

Meeting-Briefs

Will County Public Health & Safety Committee July 3 Meeting Briefs

Grain Dust Complaint Prompts Investigation: Will County resident Tracy Henning of unincorporated Peotone addressed the committee about health problems she attributes to grain dust from a neighboring facility. Henning, who...
Will-County-Legislative-Committee-Meeting-July-1-2025

Will County Seeks Asian Carp Provision in Federal Legislative Agenda

Will County Board member Julie Berkowicz is pushing to add specific language addressing Asian carp invasion to the county's federal legislative agenda, citing the ongoing threat to local waterways as...
Will-County-Capital-Improvements-IT-Committee-Meeting-July-1-2025

Will County’s Major Capital Projects Hit Key Milestones, VAC Buildout on “Aggressive Schedule”

Will County is making significant headway on several major capital improvement projects, with the new Veterans Assistance Commission (VAC) & Support Center in Joliet on an “aggressive schedule” for a...
Will-County-Legislative-Committee-Meeting-July-1-2025

State Legislative Session Update: Transit, Energy Bills Stall Despite Democratic Control

Illinois lawmakers failed to advance major transit funding and comprehensive energy legislation during the recently concluded spring session, leaving key issues unresolved despite Democratic supermajorities in both chambers, according to...
Will-County-Public-Works-Transportation-Committee-Meeting-July-1-2025

County Board Approves 2026-2031 Transportation Plan Despite Project Opposition

Will County board members approved a contested five-year transportation improvement plan Tuesday after heated debate over a controversial Homer Glen road project that has drawn sustained community opposition. The Will...
Will-County-Planning-and-Zoning-Commission-Meeting-July-1-2025

Contentious I-3 Rezoning for DuPage Township Storage Yard Narrowly Advances

A proposal to rezone a 20-acre parcel in DuPage Township from agricultural to the county's most intensive industrial classification narrowly earned a recommendation for approval from the Will County Planning...
Meeting-Briefs

Will County Legislative Committee July 1 Meeting Briefs

Federal Budget Impact: Will County could face significant funding challenges if federal budget reconciliation measures reduce Medicaid and SNAP benefits. The county health department and social services rely heavily on...
Will-County-Finance-Committee-Meeting-July-1-2025

County Moves Forward with $200.8 Million Bond Refinancing Plan

Will County Finance Committee members on July 1 approved moving forward with a comprehensive bond refinancing ordinance that could save taxpayers more than $716,000 over the life of the bonds...
Will-County-Public-Works-Transportation-Committee-Meeting-July-1-2025

Access Will County Dial-a-Ride Program Sees Record Growth, Eyes Expansion

Will County's dial-a-ride transportation service for seniors and disabled residents reached record ridership levels while officials plan major expansion to cover all county townships. The Access Will County program served...
Will-County-Capital-Improvements-IT-Committee-Meeting-July-1-2025

Will County to Launch New Public Meeting Agenda System in August Amidst Data Conversion Concerns

Will County is set to launch its new public meeting agenda and records software, Granicus “OneMeeting,” in August, but the transition will see over a decade of historical records converted...
Will-County-Planning-and-Zoning-Commission-Meeting-July-1-2025

Green Garden Township Poised for First Major Subdivision in Years After Rezoning

The Will County Planning and Zoning Commission has recommended a rezoning that could pave the way for the first major residential subdivision in Green Garden Township in nearly two decades....
Will-County-Finance-Committee-Meeting-July-1-2025

County RNG Facility Shows Strong Performance Despite Solar Challenges

Will County's Renewable Natural Gas facility is exceeding production targets while officials explore options to reduce substantial electricity costs that currently impact profitability. Project manager Greg Komperda told Finance Committee...
Meeting-Briefs

PZC Briefs: Solar Farm in Crete, Post-Fire Permit for Troy Business, and More

The Will County Planning and Zoning Commission handled several other cases during its July 1 meeting, including a new solar farm, a temporary permit for a fire-damaged business, and routine...
Meeting-Briefs

In Brief: Capital & IT News

Here are other highlights from the Will County Capital Improvements & IT Committee meeting on Tuesday. Successful Fire Drill at County BuildingThe Will County Office Building held its first full...
Meeting-Briefs

Will County Finance Committee July 1 Meeting Briefs

Bond Refinancing Advances: Finance Committee approved an ordinance authorizing up to $200.8 million in bond refinancing that could save taxpayers more than $716,000. The measure moves to the full County...