Will County Approves $2.9 Million Engineering Contract for Bluff Road Reconstruction in Channahon

Spread the love

Will County Public Works & Transportation Committee Meeting | April 7, 2026

Article Summary: The county is advancing a massive overhaul of Bluff Road in Channahon, approving a nearly $3 million Phase I and II engineering contract to prepare the corridor for full reconstruction, storm sewers, and potential retaining walls.

Bluff Road Engineering Key Points:

  • The committee approved a $2,955,607 contract with Peralte-Clark, LLC.

  • The project covers Bluff Road (CH 77) from the I-55 West Frontage Road to US Route 6.

  • The design will convert the existing rural, ditch-lined road into an urban cross-section with curb, gutter, and storm sewers.

  • The contract includes extensive geotechnical and environmental investigations due to the likelihood of encountering shallow bedrock and utility conflicts.

The Will County Board Public Works & Transportation Committee on Tuesday, April 7, 2026, unanimously approved a sweeping $2,955,607 professional services agreement with Peralte-Clark, LLC to engineer the total reconstruction of Bluff Road in Channahon.

The project targets a 5,900-foot, 1.1-mile stretch of Bluff Road (County Highway 77) between US Route 6 and the West Frontage Road of Interstate 55. Currently a two-lane major collector carrying roughly 5,850 vehicles per day, the roadway suffers from pavement deterioration, geometric deficiencies, and drainage issues.

According to the project scope detailed in the agenda packet, Peralte-Clark will guide the project through both Phase I (Preliminary & Environmental Engineering) and Phase II (Design Engineering). The ultimate goal is to convert the existing rural cross-section—characterized by aggregate shoulders and open ditches—into a modernized urban section featuring concrete curbs, gutters, and an enclosed storm sewer system.

The engineering task is highly complex due to the corridor’s specific geography. The contract includes significant subsurface investigations by subconsultants to identify areas of shallow bedrock, which could severely impact drainage design, excavation costs, and the placement of proposed retaining walls.

The Phase I study will evaluate up to four geometric alternatives, including two-lane and three-lane configurations, while also designing pedestrian and bicycle accommodations. The engineering team will also be required to navigate substantial utility conflicts, requiring a dedicated Subsurface Utility Engineering (SUE) evaluation.

The $2.95 million contract will be funded through a combination of County Motor Fuel Tax, RTA Tax, Highway Tax, and Matching Tax funds. According to the preliminary schedule, Phase II design is slated for completion by March 2027, with construction potentially beginning in June 2027.

Leave a Comment





Latest News Stories

Frankfort-Village-Board-Meeting-Graphic-June-16-2025

Frankfort Approves Outdoor Patios for The Loft and Grounded Coffee Bar, Waives All Parking Requirements

Downtown Frankfort is set to expand its outdoor dining options after the Village Board on Monday approved plans for new patios at two adjacent businesses, The Loft and Grounded Coffee...
Frankfort-Village-Board-Meeting-Graphic-June-16-2025

Frankfort Police Department to Get Four New Vehicles in Fleet Upgrade

FRANKFORT, Ill. – The Frankfort Police Department will be updating its aging fleet after the Village Board approved the purchase of four new vehicles for a total cost not to...
Frankfort-Village-Board-Meeting-Graphic-June-16-2025

Indoor Pickleball Facility ‘Pickled!’ Gets Green Light in Frankfort

A new indoor pickleball facility named "Pickled!" is set to open in Frankfort after the Village Board granted a special use permit for the business at its Monday meeting. The...
Frankfort-Village-Board-Meeting-Graphic-June-16-2025

Frankfort to Install Public Wi-Fi at Breidert Green

Visitors to Breidert Green in downtown Frankfort will soon have access to free public wireless internet. The Village Board on Monday approved the purchase and installation of Wi-Fi equipment to...
Frankfort-Village-Board-Meeting-Graphic-June-16-2025

Frankfort Board Approves Indoor Recreation Facility and Setback Variance

The Frankfort Village Board gave its approval to two separate development projects Monday night, clearing the way for a new indoor pickleball facility and a residential addition. Trustees unanimously granted...
Frankfort-Village-Board-Meeting-Graphic-June-16-2025

Meeting Briefs: Frankfort Village Board for June 16, 2025

Downtown Patios Approved, Parking Waived: The Village Board approved outdoor seating for The Loft and Grounded Coffee Bar on Ash Street. To support the downtown businesses, trustees also voted to waive...
Will-County-Executive-Committee-Meeting-June-12-2025

Mental Health Board Awards $5 Million in Grants to Will County Organizations

The Will County Community Mental Health Board has distributed over $5 million in grants to 39 local organizations, marking the completion of its inaugural funding cycle since voters approved the...
frankfort-square-park-district.2

Frankfort Square Park District Adopts Budget and Appropriation Ordinance, Updates Financial Policy

The Frankfort Square Park District Board of Commissioners formally adopted its Budget and Appropriation Ordinance for the 2025-2026 fiscal year on Thursday, finalizing the district's legal spending authority for the...
Will-County-Executive-Committee-Meeting-June-12-2025

County Board Approves Major Code Updates, Discusses Employee Benefits

The Will County Board Executive Committee approved several ordinance updates Wednesday while engaging in detailed discussions about employee compensation and benefits. The committee passed ordinances updating three chapters of the...
frankfort-square-park-district.1

Major Park District Projects Advance as Hunter Prairie Park Gets Green Light

Work on the Frankfort Square Park District's three major capital projects is hitting key milestones, with the long-awaited redevelopment of Hunter Prairie Park now officially underway. Executive Director Audrey Marcquenski...
Meeting-Briefs

Executive Committee June 12 Meeting Briefs

Property Purchase Approved: The county authorized purchase of two parcels along Governor's Highway in Monee for $545,000 to establish a roadway maintenance facility for the eastern end of the county....
frankfort-square-park-district.2

Developer to Donate Land, Playground for New Park in Tinley Park

A new park is coming to a Tinley Park development thanks to a land and equipment donation from a local home builder. Frank Bradley, owner of Crana Homes, is donating...
Meeting-Briefs

Meeting Briefs: Frankfort Square Park District for June 12, 2025

The Frankfort Square Park District Board of Commissioners formally adopted its annual Budget and Appropriation Ordinance on June 12, a key legal step that sets the district’s spending authority for...
frankfort-school-district-161.2-e1754272831494

Summit Hill Board Approves School Resource Officer for Two Schools in Contentious Vote

The Summit Hill School District 161 Board of Education voted to hire a School Resource Officer (SRO) to serve two of its schools, approving an annual expenditure of up to...
frankfort-school-district-161.1

Summit Hill School Board Reverses Controversial Principal Non-Renewal Decision

In a significant reversal, the Summit Hill School District 161 Board of Education voted to repeal previous resolutions that aimed to not renew the contract of an unnamed principal, effectively...