Nessel pushes back as Trump administration extends order keeping coal plant open

Nessel pushes back as Trump administration extends order keeping coal plant open

Spread the love

The Trump administration has again extended its emergency order keeping a west Michigan coal plant operating.

U.S. Energy Secretary Chris Wright issued a fifth emergency order earlier this week requiring the J.H. Campbell coal plant in West Olive to remain available through Aug. 16, extending operations more than a year past its original retirement date.

The Campbell plant, which began operating in 1962 and is owned by Consumers Energy, is the utility’s last remaining coal-fired power plant. The facility generates enough electricity to serve roughly 1 million people.

The latest order follows a series of previous 90-day extensions. The Department of Energy has argued the Midcontinent Independent System Operator, or MISO, faces ongoing resource concerns and risks of electricity shortfalls during periods of high demand or low generation output.

“The continued operation of the Campbell Plant would provide additional generation capacity during these periods, which would help prevent the potential loss of power to homes and local businesses in the areas that might have been affected by curtailments or outages that would otherwise pose a risk to public health and safety,” the latest order stated. “The continued operation of the Campbell Plant was necessary to alleviate immediate and anticipated threats to reliability.”

The Department of Energy said the plant proved critical during recent winter storms and argued shutting it down would worsen grid reliability challenges across the Midwest heading into the summer months.

“The energy sources that perform when you need them most are inherently the most valuable – that’s why beautiful, clean coal was the MVP during peak capacity events this past year,” Wright said in a statement announcing the extension. “Hundreds of American lives have likely been saved because of President Trump’s actions saving America’s coal plants, including this Michigan coal plant which ran daily during Winter Storm Fern. This emergency order will mitigate the risk of blackouts and maintain affordable, reliable, and secure electricity access across the region this summer.”

The latest order directs MISO, in coordination with Consumers Energy, to ensure the plant remains available to operate while minimizing costs.

A July 2025 report from the U.S. Department of Energy argued the U.S. will face a significantly increased risk of power outages by 2030 if scheduled coal and natural gas plant retirements are allowed to proceed, as previously reported by The Center Square.

The report fulfilled a direction by President Donald Trump in an April 2025 executive order to “develop a uniform methodology for analyzing current and anticipated reserve margins for all regions of the bulk power system.”

Last year, Michigan joined a coalition of states challenging that report. Michigan Attorney General Dana Nessel, a Democrat, joined community leaders and environmental advocates in Ottawa County on Thursday to call for the plant’s immediate closure.

“The real energy emergency is the one Trump himself is creating,” Nessel said. “Meanwhile, the JH Campbell coal plant has cost hundreds of millions of dollars to operate – costs Michigan ratepayers will be forced to pay. We will be intervening to stop the most recent extension and will do so as many times as necessary to protect Michigan residents from these unlawful orders.”

Last week, environmental groups and the attorneys general of Michigan, Minnesota and Illinois argued before the U.S. Court of Appeals for the District of Columbia Circuit that the DOE is unlawfully using its emergency powers to keep the plant open.

It’s not without increased cost as well.

The Environmental Defense Fund has pointed to recent regulatory filings showing the plant’s continued operation has already added roughly $180 million in costs through March 2026, or more than $600,000 per day. The organization said Consumers Energy is seeking to recover those costs from ratepayers.

“For almost a year now, Midwestern families and businesses have been left footing the bill for a costly, polluting coal plant they don’t need and they can’t afford,” said Ted Kelly, Director and Lead Counsel, U.S. Clean Energy at Environmental Defense Fund. “Abusing emergency powers in this way sets a terrible precedent for grid planning . . . the Department of Energy is throwing all those years of state and local planning out the window, forcing people to pay the price of costly coal power indefinitely.”

The Trump administration has issued similar emergency orders extending operations at several other coal plants nationwide, including ones in Indiana, Colorado, and Washington.

Leave a Comment





Latest News Stories

Chicago transit violent crime at 7 year high, funding concerns persist

Chicago transit violent crime at 7 year high, funding concerns persist

By Glenn Minnis | The Center Square contributorThe Center Square (The Center Square) – With federal authorities now threatening to cut Chicago Transit Authority funding due to rising violence across...
WATCH: National Guard case before SCOTUS; Trump insists China soybean deal coming

WATCH: National Guard case before SCOTUS; Trump insists China soybean deal coming

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square Editor Greg Bishop reviews the latest...
Screenshot 2025-10-17 at 11.31.38 AM

Lincoln-Way Board Honors Students with Perfect ACT Scores, Music Educator of the Year

LW210 Board of Education Meeting | October 16, 2025 Article Summary: Lincoln-Way District 210 celebrated exceptional academic and faculty achievement by formally recognizing nine students who earned a perfect composite...
Meeting Briefs

Meeting Summary and Briefs: Peotone Board of Education for September 29, 2025

Peotone School Board Special Board Meeting - Monday, September 29, 2025 The Peotone Board of Education held a special meeting on Monday, September 29, 2025, primarily to pass a revised...
Meeting-Briefs-4

Meeting Summary and Briefs: Green Garden Township for October 13, 2025

The Green Garden Township Board meeting on Monday, October 13, 2025, was dominated by two major issues: a growing community-led fight against a massive proposed solar facility and the board's...
Screenshot 2025-10-17 at 11.32.04 AM

Lincoln-Way Support Staff Union Rejects Tentative Contract Agreement

LW210 Board of Education Meeting | October 16, 2025 Article Summary: Members of the Lincoln-Way Community High School District 210 support staff union have voted down a tentative five-year contract...
Screenshot 2025-10-16 at 8.29.54 PM

Green Garden Abandons Town Hall Project, Forfeits Grant After County Shortens Deadline

Green Garden Township Meeting October 13 @ 7PM Article Summary: The Green Garden Township Board has officially withdrawn from a grant-funded project for a new town hall after Will County...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Legislative Committee for October 7, 2025

The Will County Legislative Committee held a long and contentious meeting on Tuesday, October 7, 2025, highlighted by the narrow 4-3 passage of a controversial resolution supporting protections for immigrant...
Screenshot 2025-10-17 at 11.13.13 AM

Peotone School Board Passes Revised Budget, Averting Financial Shutdown

Peotone School Board Special Board Meeting - Monday, September 29, 2025 Article Summary: Facing a state-mandated deadline, the Peotone Board of Education narrowly passed a revised 2025-2026 budget with a...
Screenshot 2025-10-16 at 8.30.46 PM

Green Garden Residents Mobilize Against Massive 18-Square-Mile Solar Facility

Green Garden Township Meeting October 13 @ 7PM Article Summary: A volunteer citizen group in Green Garden Township has announced a five-phase strategy to stop a massive commercial solar facility...
Meeting Briefs

Meeting Summary and Briefs: Peotone Board of Education for September 22, 2025

The Peotone school board on Monday, September 22, 2025, rejected the district's 2025-2026 budget, which carried a $4.2 million deficit, setting off an urgent scramble to find significant cuts before...
Screenshot 2025-10-10 at 12.05.55 PM

Will County Board Committee Passes Contentious ‘Live and Work Without Fear’ Resolution on 4-3 Vote

Will County Legislative Committee Meeting October 7, 2025 Article Summary: The Will County Legislative Committee on Tuesday narrowly passed a controversial resolution affirming the county's commitment to ensuring all residents...
Meeting Briefs

Will County Awards $10.4 Million Contract for Bell Road Widening in Homer Glen Area

Will County Public Works & Transportation Committee Meeting October 7, 2025 Article Summary: The Will County Public Works & Transportation Committee on Tuesday confirmed the award of a $10.4 million...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Finance Committee for October 7, 2025

The Will County Finance Committee on Tuesday, October 7, 2025, held a contentious meeting centered on the county’s finances, narrowly approving a preliminary $161.6 million county-wide tax levy on a...
Screenshot 2025-10-10 at 12.12.16 PM

Meeting Summary and Briefs: Will County Public Works & Transportation Committee for October 7, 2025

The Will County Public Works & Transportation Committee on Tuesday, October 7, 2025, approved a major construction contract and reviewed extensive plans for both county and state transportation initiatives. The...