County RNG Facility Shows Strong Performance Despite Solar Challenges

Will County’s Renewable Natural Gas facility is exceeding production targets while officials explore options to reduce substantial electricity costs that currently impact profitability.

Project manager Greg Komperda told Finance Committee members July 1 that the facility has operated at 94-95% capacity for three consecutive months, representing full operational capacity. Production has consistently exceeded both targets and minimum contractual obligations.

“We met our production targets in April, May, and June,” Komperda reported. The facility generated $5.26 million in revenue through June 20 against $3.89 million in expenses, though debt service payments result in approximately $1.2 million negative cash flow.

County Board member Julie Berkowicz questioned whether solar power could help offset electricity costs, noting the facility’s consumption of 3,500 kilowatts per hour. Dave Hartke, director of Land Use, explained that meeting those power needs would require 40-50 acres of solar panels.

“You’re probably looking at a solar farm around maybe 40 50 acres maybe around there to supply the electricity for the plant,” Hartke said. “At this point there’s no room around unless we’ve had to create a solar farm adjacent property.”

Any solar development faces complications from uncertainty about potential landfill expansion. Officials indicated they prefer to wait until expansion decisions are made before committing to permanent solar installations.

Daniel Butler noted that a complete solar installation could cost hundreds of millions of dollars, questioning the return on investment. Officials acknowledged that even partial solar power could help reduce costs but emphasized the need for careful analysis of long-term planning.

The facility successfully hosted tours in June and has improved spare parts inventory planning to reduce downtime risks. Despite minor operational challenges including utility outages and equipment repairs, the facility has maintained strong performance metrics above the 92% target runtime.

Events

No events

Leave a Comment





Latest News Stories

Will-County-Public-Works-Transportation-Committee-Meeting-July-1-2025

Access Will County Dial-a-Ride Program Sees Record Growth, Eyes Expansion

Will County's dial-a-ride transportation service for seniors and disabled residents reached record ridership levels while officials plan major expansion to cover all county townships. The Access Will County program served...
Will-County-Capital-Improvements-IT-Committee-Meeting-July-1-2025

Will County to Launch New Public Meeting Agenda System in August Amidst Data Conversion Concerns

Will County is set to launch its new public meeting agenda and records software, Granicus “OneMeeting,” in August, but the transition will see over a decade of historical records converted...
Will-County-Planning-and-Zoning-Commission-Meeting-July-1-2025

Green Garden Township Poised for First Major Subdivision in Years After Rezoning

The Will County Planning and Zoning Commission has recommended a rezoning that could pave the way for the first major residential subdivision in Green Garden Township in nearly two decades....
Will-County-Finance-Committee-Meeting-July-1-2025

County RNG Facility Shows Strong Performance Despite Solar Challenges

Will County's Renewable Natural Gas facility is exceeding production targets while officials explore options to reduce substantial electricity costs that currently impact profitability. Project manager Greg Komperda told Finance Committee...
Meeting-Briefs

PZC Briefs: Solar Farm in Crete, Post-Fire Permit for Troy Business, and More

The Will County Planning and Zoning Commission handled several other cases during its July 1 meeting, including a new solar farm, a temporary permit for a fire-damaged business, and routine...
Meeting-Briefs

In Brief: Capital & IT News

Here are other highlights from the Will County Capital Improvements & IT Committee meeting on Tuesday. Successful Fire Drill at County BuildingThe Will County Office Building held its first full...
Meeting-Briefs

Will County Finance Committee July 1 Meeting Briefs

Bond Refinancing Advances: Finance Committee approved an ordinance authorizing up to $200.8 million in bond refinancing that could save taxpayers more than $716,000. The measure moves to the full County...
Meeting-Briefs

Will County Public Works Committee Juliy 1 Meeting Briefs

ROAD CONTRACTS APPROVED Austin Tyler Construction Contract: The committee approved a $691,544 contract with Austin Tyler Construction for resurfacing River Road from East Frontage Road to Prairie Creek Bridge and...
Screenshot 2025-07-08 at 2.34.06 PM

Green Garden Township Weighs Youth Sports Partnership for Community Development

Green Garden Township could become home to expanded youth football facilities under a proposal presented at Thursday's special meeting, as local sports programs seek permanent venues amid community facility discussions....
Meeting-Briefs-1

Green Garden Town Hall June 26 Meeting Briefs

Grant Deadline Approaches: Green Garden Township must decide on facility plans by the end of 2026 to retain $400,000 in remaining Will County grant funding. The township has already invested...
JJC-Graphic-Logo

JJC Trustees Approve Contentious FY26 Budget After Heated Debate, Failed Postponement

The Joliet Junior College Board of Trustees on Wednesday approved a $322.3 million budget for fiscal year 2026, but not before a tense debate that saw a motion to postpone...
Joliet-Junior-college.-Graphic-Logo.5

JJC’s ‘12x12x12’ Initiative Boosts College Credits, Increases Matriculation Rate

Joliet Junior College’s ambitious "12x12x12" initiative is yielding significant results, leading to more high school students earning college credits and a greater percentage of them choosing to attend JJC after...
Joliet-Junior-college.-Graphic-Logo.4

JJC Board Meeting Highlights Tensions Over Legal Bills, Trustee Conduct

An otherwise routine vote to approve monthly bill payments ignited a tense exchange at the Joliet Junior College Board of Trustees meeting Wednesday, revealing ongoing friction over redacted legal invoices,...
Joliet-Junior-college.-Graphic-Logo.3

Students, Trustees Emphasize Importance of Inclusivity and Flag Raisings at JJC

From a recent graduate’s public plea to trustee remarks on federal policies, the theme of student belonging and inclusivity was a prominent thread at the Joliet Junior College Board of...
Joliet-Junior-college.-Graphic-Logo.2

JJC Embarks on New 10-15 Year Facilities Master Plan Process

Joliet Junior College is laying the groundwork for its physical future, officially launching a comprehensive process to create a new facilities master plan that will guide campus development for the...