Key Stretch of Bell Road on Track for Thanksgiving Reopening, Committee Approves Additional Funds

ARTICLE SUMMARY Construction on Bell Road between 159th and 151st Streets is scheduled to have all lanes open by Thanksgiving, officials announced as the Public Works & Transportation Committee approved a $652,896 supplemental contract for engineering services.


Key Points:

  • The Thanksgiving target for reopening all lanes was confirmed by Director of Transportation Jeff Ronaldson.

  • The supplemental agreement with AECOM Technical Services, Inc., is for continued construction engineering oversight as the project extends due to utility conflict delays.

JOLIET—Commuters navigating construction on Bell Road received good news Tuesday, as Will County’s transportation director announced that all lanes on the key stretch between 159th Street and 151st Street are expected to be open by Thanksgiving.

The update came as the Will County Public Works & Transportation Committee approved a supplemental professional services agreement for $652,896 with AECOM Technical Services, Inc., for continued construction engineering on the project.

“Essentially all lanes will be open by Thanksgiving,” Director of Transportation Jeff Ronaldson told the committee. He added that some minor work, such as landscaping and final surfacing, could carry over into the spring.

The contract extension with AECOM covers the cost of having the resident engineer and consulting firm oversee construction, which was extended due to delays caused by utility conflicts. The project involves the reconstruction and widening of the heavily traveled corridor in County Board District 4.

Board Member Steve Balich (R-Homer Glen) questioned Ronaldson about the timeline, noting that residents are “jumping up and down out there, which I get it.” Ronaldson confirmed the Thanksgiving target, solidifying the timeline for the much-anticipated reopening. The committee approved the supplemental agreement unanimously.

Events

No events

Leave a Comment





Latest News Stories

MFPD-Logo-Fire-District-11

Fire District May 21 Meeting Briefs

Policy Manual Nearly Complete: The district's operational procedures and policy manual is 95% complete, with attorney review and union input ongoing. The complete manual will be presented to the board...
default

Lincoln-Way Board Approves Up to $31.3 Million Bond Sale for Safety, Security Upgrades

The Lincoln-Way Community High School District 210 Board of Education unanimously approved a resolution to issue up to $31.33 million in life safety bonds to fund a wide range of...
frankfort-square-park-district.2

Frankfort Square Park District Approves Budget Amid County Tax Adjustment, Funds Major Projects

The Frankfort Square Park District Board of Commissioners unanimously approved its operating budget for the 2025-2026 fiscal year during its April 17 meeting, earmarking funds for major ongoing projects and...
default

Lincoln-Way School Board Certifies Election, Re-elects Janik as President

The Lincoln-Way Community High School District 210 Board of Education officially reorganized for the upcoming year during its meeting on April 17, certifying the results of the April 1 consolidated...
lincoln-way-school-district.3-scaled-e1750128024313

New Electricity Contract to Save Lincoln-Way Over $500,000 Next Year

Lincoln-Way High School District 210 is poised for significant energy cost savings after the Board of Education unanimously approved a new 54-month electric commodity contract with Direct Energy. The agreement,...
frankfort-square-park-district.1

Four New Commissioners to Join Frankfort Square Park District Board in May

Four newly elected commissioners are set to join the Frankfort Square Park District Board in May, following the April 1, 2025, Consolidated Election. Executive Director Audrey Marcquenski formally congratulated Lauren...
Meeting-Briefs

Meeting Briefs: Frankfort Square Park District for April 17, 2025

The Frankfort Square Park District Board of Commissioners met on April 17 to approve its annual budget, discuss new projects, and hear departmental updates. The district approved a nearly $5...
lincoln-way-school-district.3-scaled-e1750128024313

Lincoln-Way District 210 Board Briefs

District Finances Stable in March ReportAssistant Superintendent Michael Duback presented the Treasurer’s Report for the month ending March 31, 2025. Revenues for the month totaled $3.1 million, while expenditures were...
Frankfort-Township-Logo-Graphic

Frankfort Township Board Unanimously Opposes Government Consolidation

The Frankfort Township Board on Monday took a firm stance against a perennial issue in Illinois politics, unanimously passing a resolution to formally oppose any legislative efforts to consolidate or...
Frankfort-Township-Logo-Graphic

Frankfort Township Upgrading Senior Apartments Amidst High Demand

Frankfort Township is moving forward with significant upgrades to its senior apartments to meet modern standards, Supervisor Nick George announced at Monday’s board meeting. The improvements come as the township...
Frankfort-Township-Logo-Graphic

Outdoor Bar Expansion Gets Green Light from Frankfort Township

The Frankfort Township Board has approved a special use permit that will allow a bar in an unincorporated area to expand its service outdoors. The unanimous decision was made during...
Frankfort-Township-Logo-Graphic

Meeting Briefs: Frankfort Township Board for April 14, 2025

The Frankfort Township Board of Trustees met on Monday, April 14, 2025, to address zoning matters and new business. The board took a firm stance against government consolidation, unanimously passing...
Green-Garden-Logo.WP

Comprehensive Plan Update Proceeds Despite Request from Incoming Officials

GREEN GARDEN TOWNSHIP — The Green Garden Township Planning Commission is moving forward with updating the township's comprehensive plan despite renewed requests from incoming elected officials to put the project...
Green-Garden-Logo.WP

Township Sees Significant Growth as Assessor Reports 39 New Home Construction Sites

GREEN GARDEN TOWNSHIP — Green Garden Township is experiencing substantial residential growth with 39 new home construction sites currently underway, according to a report delivered by Township Assessor Bushong at...
Green-Garden-Logo.WP

Township Trustee Defends Building Renovation Project, Addresses Parking Concerns

GREEN GARDEN TOWNSHIP — Trustee Wagner provided information about the township's building renovation project at the February meeting, responding to concerns raised at the previous month's session and clarifying several...