Renovations at Veterans Assistance Commission and Court Annex on Track for Winter Completion

Spread the love

Article Summary: Will County’s new Veterans Assistance Commission facility in Joliet is projected to be completed by December, while major renovations for the State’s Attorney’s office in the Court Annex are on schedule for a November move-in. Director of Facilities Bill Fern updated a county committee on the progress of these and other key capital projects across the county.

Capital Projects Update Key Points:

  • Interior renovations at the Veterans Assistance Commission buildout at 1300 Copperfield are underway, with a target completion of December 2025.

  • The Court Annex renovations for the State’s Attorney’s office at 57 N. Ottawa are nearing completion and on track for a November 2025 move-in.

  • A potential delay in the delivery of rooftop air handlers for the VAC building is being monitored by the facilities department.

  • Other completed projects include exterior stone repairs at the new courthouse and the installation of speed bumps at the county office building.

JOLIET, IL — Two major Will County building projects are nearing the finish line, with the new Veterans Assistance Commission (VAC) facility expected to open by December and the State’s Attorney’s office set to move into its renovated space in November.

Will County Director of Facilities Bill Fern provided the updates to the Capital Improvements & IT Committee on Tuesday, October 7, 2025.

The buildout of the former Copperfield building at 1300 Copperfield for the VAC is progressing well, with mechanical, lighting, and security systems currently being installed. Fern noted one potential issue that staff is monitoring closely. “The air handling units for the rooftop… the timeline for shipment has been delayed twice,” he said. “We’re coming into the critical point where we’re going to need to condition the space for heat, not air.” Despite the potential delay, the project is still aiming for completion by the end of the year.

Meanwhile, renovations on the second level of the Court Annex building at 57 N. Ottawa for the State’s Attorney’s office are moving quickly. “We’re in a finished space now with the carpet down,” Fern reported, adding that the project is on track for its November move-in date. The remodel includes opening up previously sealed windows to provide natural light to the new offices.

Fern also reported on several smaller projects, including the recent installation of speed bumps and fresh striping in the parking lot of the Will County Office Building to improve pedestrian safety. He also noted that exterior stone repairs on the new courthouse are complete, with scaffolding now removed, at no cost to the county.

Events

No events

Leave a Comment





Latest News Stories

Will-County-Public-Works-Transportation-Committee-Meeting-July-1-2025

Access Will County Dial-a-Ride Program Sees Record Growth, Eyes Expansion

Will County's dial-a-ride transportation service for seniors and disabled residents reached record ridership levels while officials plan major expansion to cover all county townships. The Access Will County program served...
Will-County-Capital-Improvements-IT-Committee-Meeting-July-1-2025

Will County to Launch New Public Meeting Agenda System in August Amidst Data Conversion Concerns

Will County is set to launch its new public meeting agenda and records software, Granicus “OneMeeting,” in August, but the transition will see over a decade of historical records converted...
Will-County-Planning-and-Zoning-Commission-Meeting-July-1-2025

Green Garden Township Poised for First Major Subdivision in Years After Rezoning

The Will County Planning and Zoning Commission has recommended a rezoning that could pave the way for the first major residential subdivision in Green Garden Township in nearly two decades....
Will-County-Finance-Committee-Meeting-July-1-2025

County RNG Facility Shows Strong Performance Despite Solar Challenges

Will County's Renewable Natural Gas facility is exceeding production targets while officials explore options to reduce substantial electricity costs that currently impact profitability. Project manager Greg Komperda told Finance Committee...
Meeting-Briefs

PZC Briefs: Solar Farm in Crete, Post-Fire Permit for Troy Business, and More

The Will County Planning and Zoning Commission handled several other cases during its July 1 meeting, including a new solar farm, a temporary permit for a fire-damaged business, and routine...
Meeting-Briefs

In Brief: Capital & IT News

Here are other highlights from the Will County Capital Improvements & IT Committee meeting on Tuesday. Successful Fire Drill at County BuildingThe Will County Office Building held its first full...
Meeting-Briefs

Will County Finance Committee July 1 Meeting Briefs

Bond Refinancing Advances: Finance Committee approved an ordinance authorizing up to $200.8 million in bond refinancing that could save taxpayers more than $716,000. The measure moves to the full County...
Meeting-Briefs

Will County Public Works Committee Juliy 1 Meeting Briefs

ROAD CONTRACTS APPROVED Austin Tyler Construction Contract: The committee approved a $691,544 contract with Austin Tyler Construction for resurfacing River Road from East Frontage Road to Prairie Creek Bridge and...
Screenshot 2025-07-08 at 2.34.06 PM

Green Garden Township Weighs Youth Sports Partnership for Community Development

Green Garden Township could become home to expanded youth football facilities under a proposal presented at Thursday's special meeting, as local sports programs seek permanent venues amid community facility discussions....
Meeting-Briefs-1

Green Garden Town Hall June 26 Meeting Briefs

Grant Deadline Approaches: Green Garden Township must decide on facility plans by the end of 2026 to retain $400,000 in remaining Will County grant funding. The township has already invested...
JJC-Graphic-Logo

JJC Trustees Approve Contentious FY26 Budget After Heated Debate, Failed Postponement

The Joliet Junior College Board of Trustees on Wednesday approved a $322.3 million budget for fiscal year 2026, but not before a tense debate that saw a motion to postpone...
Joliet-Junior-college.-Graphic-Logo.5

JJC’s ‘12x12x12’ Initiative Boosts College Credits, Increases Matriculation Rate

Joliet Junior College’s ambitious "12x12x12" initiative is yielding significant results, leading to more high school students earning college credits and a greater percentage of them choosing to attend JJC after...
Joliet-Junior-college.-Graphic-Logo.4

JJC Board Meeting Highlights Tensions Over Legal Bills, Trustee Conduct

An otherwise routine vote to approve monthly bill payments ignited a tense exchange at the Joliet Junior College Board of Trustees meeting Wednesday, revealing ongoing friction over redacted legal invoices,...
Joliet-Junior-college.-Graphic-Logo.3

Students, Trustees Emphasize Importance of Inclusivity and Flag Raisings at JJC

From a recent graduate’s public plea to trustee remarks on federal policies, the theme of student belonging and inclusivity was a prominent thread at the Joliet Junior College Board of...
Joliet-Junior-college.-Graphic-Logo.2

JJC Embarks on New 10-15 Year Facilities Master Plan Process

Joliet Junior College is laying the groundwork for its physical future, officially launching a comprehensive process to create a new facilities master plan that will guide campus development for the...