Will County completes major projects while others move forward

Will County’s facilities team has completed several major projects while advancing others throughout the county, officials reported during a Capital Improvements & IT Committee meeting Monday.

The Old Courthouse Plaza concrete replacement project at 14 W. Jefferson has been finished, with new picnic benches installed and the area fully restored with handicap-accessible ramps meeting current ADA standards, according to Facilities Director Bill Fern.

“The plaza is completely usable again, safe level, all new concrete, all handicap ramps all been replaced,” Fern told committee members during his monthly facilities update.

The county has also completed parking lot resurfacing at both the Community Health Center and River Valley Juvenile Detention Center. The River Valley project addressed serious deterioration issues and brought handicap ramps up to current ADA compliance standards after the original construction was determined to be too steep by today’s requirements.

“That parking lot was in serious need of resurfacing,” Fern said. “The handicap ramps, the ADA accessible areas when they built it were too steep to today’s standards, so now they are all compliant.”

Work continues on several other major projects across county properties. The Court Annex/State’s Attorney Level 2 renovations at 57 N. Ottawa are scheduled to begin construction July 10 following bid openings set for June 4. The project, which involves combining unused courtrooms on the second and third floors to create more usable space, is expected to be completed by fall 2025.

Similarly, Land Use/Public Defender renovations at 58 E. Clinton are progressing with Level 3 complete and Level 4 work beginning June 16. That project is also slated for completion in August.

The Veterans Assistance Commission buildout at 1300 Copperfield has reached several milestones, with roof replacement 95% complete and both glass replacement and interior renovations set to begin June 9. The project involves UV-coated, double-pane glass replacement and is expected to wrap up in fall 2025.

Committee Chair Mica Freeman noted the county is expecting facility assessment reports by month’s end that will merge facility condition evaluations with space needs analysis. The comprehensive assessment covers 75% of county-owned properties, with the largest facilities – Adult Detention Facility and River Valley – nearing completion of their evaluations.

Fern reported his team handled over 760 work orders in May, completing them with 98% on-time performance at an average cost of $19.75 per work order. The facilities team logged more than 800 hours of labor during the month.

“The team is really moving,” Fern said, highlighting the department’s productivity while maintaining zero workplace injuries – a safety record Committee member Herbert Brooks Jr. praised as worthy of celebration.

The committee also addressed ongoing courthouse issues, with scaffolding removal underway as stone replacement work continues. Water infiltration behind limestone panels caused damage when freezing temperatures expanded the moisture, pushing stones outward. Sixteen new quarried limestone pieces are being manufactured for replacement, with installation planned using swing stages rather than scaffolding.

A facilities report from material specialists examining the courthouse damage is expected by the end of next week, providing definitive analysis of the stone failure and remediation efforts.

The next committee meeting is scheduled for July 1.

Events

No events

Leave a Comment





Latest News Stories

WCO-PZ-July-15

Will County Planners OK Oversized Garage Near Naperville, Overriding Staff Recommendation

The Will County Planning and Zoning Commission on Tuesday approved variances for a new oversized accessory garage in Wheatland Township, siding with a homeowner and builder over a staff recommendation...
WCO-PZ-July-15

Green Garden Landscaping Business Gains Permit Amid Strong Neighbor Support

A small landscaping and lawn maintenance business operating on a residential property in Green Garden Township received official approval Tuesday after neighbors voiced overwhelming support for the operation. The Will...
Meeting-Briefs

Meeting Briefs: Will County Planning and Zoning Commission for July 15, 2025

Frankfort Shed Relocation Approved: A homeowner on West Harvest Drive in Frankfort Township received a variance to reduce an east side-yard setback from 10 to 4 feet. The variance, sought by...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves ‘Whisk & Flame’ Culinary Studio, Slashes Parking Requirement for Downtown Property

An experiential culinary studio named Whisk & Flame is set to open in downtown Frankfort after the Village Board approved a series of special use permits and a significant parking...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Village Board Adopts $59.4 Million Appropriation for Fiscal Year 2026

The Frankfort Village Board has formally set its maximum legal spending limit for the upcoming fiscal year, adopting a $59,366,900 appropriation ordinance for fiscal year 2026. The measure was passed...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Establishes New Zoning Rules to Attract Data Centers

The Village of Frankfort has amended its zoning ordinance to create a specific use category for data centers, a move designed to regulate and attract high-tech development. The Village Board...
Frankfort-Village-Board-Meeting-Graphic

Currie Motors Expansion Gets Approval with Site Modifications

Currie Motors on Lincoln Highway received approval from the Frankfort Village Board on Monday for a major change to its site plan, allowing for the construction of seven new parking...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves $134,531 Maintenance Contract for Wastewater Plant Filters

The Frankfort Village Board has approved a $134,531.17 agreement with Veolia Water Technologies, Inc. for critical preventative maintenance at the Regional Wastewater Treatment Plant. The contract is for the complete...
Frankfort-Village-Board-Meeting-Graphic

Meeting Briefs: Frankfort Village Board for July 14, 2025

'Whisk & Flame' Culinary Studio Approved: The board approved "Whisk & Flame," an experiential culinary studio, for 10-12 Elwood Street. The project includes four special use permits for entertainment, liquor sales,...
WCO-Exec-Cmte-July-10.1

County Approves School Resource Officer, Multi-Year Planning Requirements

Will County approved hiring an additional sheriff's deputy for a school resource officer position that will be fully funded by Summit Hill School District 161, while also passing new transparency...
WCO-Exec-Cmte-July-10.2

County Addresses Senior Tax Exemption Processing Error

A processing error that cost County Board member Julie Berkowicz $600 in senior tax exemptions has prompted discussions about improving verification systems for property tax breaks. Will County Chief Assessment...
Meeting-Briefs

Executive Committee Meeting July 10 Meeting Briefs

Liquor License Expansion: The county approved increasing Class C1 liquor licenses from eight to nine to accommodate Lockport Gas and Food LLC at 14747 W. 159th Street in Homer Glen....
frankfort-park-district

Meeting Briefs: Frankfort Park District Board for June 10, 2025

The Frankfort Park District Board of Commissioners discussed a legal dispute with the Five Oaks homeowners association over park development rules at its Tuesday meeting. Executive Director Gina Hassett reported...
Will-County-Land-Use-July-3.1

Committee Rejects Troy Township Solar Projects Amid Strong Local Opposition

The Will County Land Use and Development Committee recommended denial for two controversial commercial solar energy projects in Troy Township on Thursday, following a wave of opposition from local municipalities,...
Will-County-Land-Use-July3.2

Controversial DuPage Township Rezoning for Outdoor Storage Advances

A contentious proposal to rezone a 20-acre parcel in DuPage Township from agricultural (A-1) to heavy industrial (I-3) for an outdoor vehicle storage facility narrowly passed the Will County Land...