ARTICLE SUMMARY: The Will County Public Works & Transportation Committee authorized two agreements totaling over $1.1 million for the ongoing reconstruction and widening of 80th Avenue between 191st and 183rd Streets.
Key Points:
-
A $1,062,982 supplemental agreement with Alfred Benesch and Company covers additional construction engineering services due to utility-related delays.
-
A separate agreement authorizes reimbursement of up to $58,556.88 to AT&T for relocating its facilities to accommodate the project.
JOLIET—A major road improvement project on 80th Avenue is moving forward after the Will County Public Works & Transportation Committee approved two agreements Tuesday worth more than $1.1 million combined.
The committee authorized a supplemental professional services agreement with Alfred Benesch and Company for $1,062,982 to cover continued construction engineering. According to project documents, the additional services are needed due to a contract extension caused by utility conflict delays.
A second agreement authorizes the county to reimburse Illinois Bell Telephone Company, doing business as AT&T, up to $58,556.88 for the cost of relocating its facilities within the project area. The work is necessary to accommodate the roadway improvements between 191st Street and 183rd Street in County Board District 4.
According to a recent construction status report, work is advancing on the Union Ditch bridge on 80th Avenue. Upcoming work includes installing timber piles for ground improvement, steel mast arms for permanent traffic signals, and conduit for a future fiber optic line for the Village of Tinley Park. The overall project includes pavement reconstruction, widening, and a new expressway overpass.
Both agreements were approved unanimously by the committee.
Latest News Stories
Beecher-Area Rezoning and Variances Approved to Legalize Structure
Committee Approves Wilton Township Land Division Despite Spot Zoning Concerns
Green Garden Residents Group Plans Lawsuit, Pushes for Township Incorporation to Fight Solar Projects
Meeting Summary and Briefs: Will County Capital Improvements & IT Committee for November 4, 2025
Green Garden Board Votes to Pursue New Town Hall, Sets December Electorate Vote
Meeting Summary and Briefs: Will County Public Works & Transportation Committee for November 2025
Will County Committee Members Debate Future Capital Priorities, Clash on Borrowing
Meeting Summary and Briefs: Will County Planning and Zoning Commission for November 4, 2025
Meeting Summary and Briefs: Will County Legislative Committee for November 4, 2025
Will County Saves $5.7 Million in Bond Refinancing, Maintains High Credit Ratings
Meeting Summary and Briefs: Joliet Junior College Board of Trustees for October 2025
Will County Saves Nearly $5.74 Million in Bond Refinancing, Explores Future Borrowing Options
Will County Board Advances New Speed Limits in Green Garden and Frankfort Townships
New Lenox Garage Variance Denied After Neighbor Cites ‘Massive’ Scale and Neighborhood Impact