Will County Receives Detailed Update on Landfill Expansion Investigation

Article Summary:

The Will County Landfill Committee received a comprehensive technical update on the site investigation for the planned horizontal expansion of the county landfill, confirming the project remains on schedule. Consultants presented detailed findings from the completed geological and hydrogeological fieldwork, which will inform the final engineering and design of the new landfill area to ensure public and environmental safety.

Landfill Expansion Key Points:

  • Drilling of nine new borings and continuous soil and bedrock sampling for the expansion area is complete, with samples being sent for extensive laboratory analysis.

  • Fourteen new piezometers, or monitoring wells, have been installed to characterize groundwater conditions and will be used for an impact evaluation model.

  • Engineers are refining the expansion’s design, including adjusting the northern boundary to maximize airspace and designing a V-notched base for efficient leachate collection.

  • Despite the fieldwork phase taking slightly longer than anticipated, project consultants confirmed the overall expansion timeline has not been delayed.

The Will County Landfill Committee on Thursday received a detailed update on the extensive site investigation for the planned expansion of the county landfill, learning that the project remains on schedule as engineers begin analyzing a trove of geological data.

A consultant for the project, Mr. Fallon, walked committee members through the now-completed fieldwork phase, which involved drilling nine borings as deep as 140 feet to characterize the soil, clay, and bedrock at the proposed expansion site. He explained that the purpose of the in-depth investigation is to provide engineers with the necessary data to design a site that protects public health, safety, and welfare.

“We have logged and continuously sampled nine additional borings to supplement that information at the existing facility,” Fallon stated. “Those samples have all been delivered to the lab. And actually… we have already received back I would say about 75% of those analytical results.”

The investigation included collecting undisturbed soil samples using Shelby tubes and rock cores to conduct a battery of laboratory tests. These tests, Fallon explained, measure properties like soil density, moisture content, permeability, and shear strength. The results are critical for engineering calculations that ensure the stability of the landfill’s slopes and foundation.

In addition to soil stability, the investigation is focused on groundwater. Fourteen new piezometers—small-diameter wells—have been installed at various depths to monitor different water-bearing zones. This data will be used to create a groundwater impact evaluation model.

“We’ll take the landfill design once it’s once our engineers have developed that and then we’ll… place it into the into the geologic system,” Fallon said in response to a question from member Dawn Bullock. “And then we’ll assume that it’s leaking and we’ll evaluate… after 100 years after closure what are the what are the concentrations of this hypothetical plume at the zone of attenuation.”

Fallon noted that this modeling is a state requirement for the sighting application.

The data is already informing design tweaks. Stormwater modeling has shown that the planned retention ponds are larger than necessary, allowing engineers to push the landfill’s northern boundary slightly to “eek out a little more airspace.” They are also designing the base grades with a “V-notch design” to better channel leachate to a sump location for extraction.

County Board Speaker Joe VanDuyne asked if the water from the underlying aquifer could be utilized by the county. Fallon explained that this would be out of the question, citing both the unsuitability of the small monitoring wells for water supply and a deed restriction on the property. “We have a deed restriction we’re not allowed to use any of the water for drinking purposes,” he said.

Vice-Chair Kelly Hickey, who chaired the meeting, asked if there were any changes to the project’s timeline.

“We haven’t had a delay in the project yet,” Fallon responded. “The field investigation did take a little longer than we than we had thought it would… but within the larger framework of the project, I feel like we’re still on schedule.”

Events

No events

Leave a Comment





Latest News Stories

Green-Garden-Logo.WP

Township Board Unites Against State Consolidation Efforts

GREEN GARDEN TOWNSHIP — The Green Garden Township Board voted unanimously to oppose state legislation that would consolidate township governments, amending the Annual Town Meeting agenda to include a resolution...
Green-Garden-Logo.WP

Planning Commission Outlines Three-Step Process for Land Use Plan

GREEN GARDEN TOWNSHIP — The Green Garden Township Planning Commission has established a three-step process for developing the township's new land use plan, with public input opportunities scheduled throughout spring,...
Green-Garden-Logo.WP

Road Projects Face Delays as Commissioner Reports Solar Leases on Needed Land

GREEN GARDEN TOWNSHIP — The planned Sheer Road bridge replacement project has been pushed back to 2026 due to utility issues, and negotiations for needed easements are complicated by solar...
Green-Garden-Logo.WP

Green Garden Township News Briefs – March 2025

Township Property Values Continue Rising: Assessor Bushong reported Green Garden Township's equalized assessed value (EAV) continues to grow rapidly, increasing by $2.5 million in just the first two months of...
Peotone-High-School-scaled-2

Peotone School Board Approves New Curriculum, Welcomes New Administrators

The Peotone Community Unit School District 207U Board of Education approved a new K-5 English Language Arts curriculum and introduced two new administrators during its April 23 meeting at Peotone...
Peotone-School-District

Peotone Students Honored for Academic and Athletic Achievements

The Peotone Board of Education recognized numerous students for their academic and athletic accomplishments during the April 23 meeting. High school sophomore Olivia Robinson was honored as the March Student...
Peotone-Junior-High-School-scaled-2

Peotone School Board Meeting Briefs

Grant Funding Secured: The district received approval for a $2,250 Illinois Literacy Plan Grant to support professional development for the new K-5 ELA curriculum implementation. Combined with $6,200 from an...
MFPD-Logo-Fire-District-3

Fire District Approves Construction Manager for New Station, Targets May 5 Bid Opening

The Manhattan Fire Protection District selected ICI Build as its construction management company for the new fire station project and is targeting May 5 for opening construction bids. The board...
MFPD-Logo-Fire-District-15

Fire District Approves Construction Manager for New Station, Targets May 5 Bid Opening

The Manhattan Fire Protection District selected ICI Build as its construction management company for the new fire station project and is targeting May 5 for opening construction bids. The board...
MFPD-Logo-Fire-District-19

Fire District Expands Health Programs, Considers Cancer Screening

The Manhattan Fire Protection District is expanding its employee wellness initiatives with potential cancer screening through body scans and continuing its successful injury prevention program. The Health and Safety Committee...
MFPD-Logo-Fire-District-4

Fire District Expands Health Programs, Considers Cancer Screening

The Manhattan Fire Protection District is expanding its employee wellness initiatives with potential cancer screening through body scans and continuing its successful injury prevention program. The Health and Safety Committee...
MFPD-Logo-Fire-District-11

Fire District May 21 Meeting Briefs

Policy Manual Nearly Complete: The district's operational procedures and policy manual is 95% complete, with attorney review and union input ongoing. The complete manual will be presented to the board...
default

Lincoln-Way Board Approves Up to $31.3 Million Bond Sale for Safety, Security Upgrades

The Lincoln-Way Community High School District 210 Board of Education unanimously approved a resolution to issue up to $31.33 million in life safety bonds to fund a wide range of...
frankfort-square-park-district.2

Frankfort Square Park District Approves Budget Amid County Tax Adjustment, Funds Major Projects

The Frankfort Square Park District Board of Commissioners unanimously approved its operating budget for the 2025-2026 fiscal year during its April 17 meeting, earmarking funds for major ongoing projects and...
default

Lincoln-Way School Board Certifies Election, Re-elects Janik as President

The Lincoln-Way Community High School District 210 Board of Education officially reorganized for the upcoming year during its meeting on April 17, certifying the results of the April 1 consolidated...