Will County’s Gas-to-Energy Plant Reports Nearly $460,000 Net Loss Amid Operational Setbacks

Spread the love

Will County Finance Committee Meeting October 7, 2025

Article Summary: Will County’s Renewable Natural Gas (RNG) plant at the county landfill posted a net loss of nearly $460,000 for the fiscal year through August, after a summer plagued by mechanical failures, power outages, and maintenance issues that hampered production. Despite the challenges, officials remain optimistic about closing the financial gap by the end of the fiscal year, pointing to a strong performance in September and the plant’s long-term revenue potential.

RNG Plant Performance Key Points:

  • As of August 31, 2025, the RNG plant reported a net loss of $459,484.52 for the fiscal year.

  • Production in July and August fell below targets due to valve failures, sensor issues, severe storms, and computer errors.

  • Production exceeded targets in June, and a strong rebound in September has officials hopeful of breaking even for the year.

  • The plant is in its third year of repaying a 12-year, $48 million green bond used for its construction.

JOLIET, IL – Will County’s gas-to-energy plant has faced a series of operational challenges this summer, resulting in a net loss of $459,484 as of August 31, according to a report presented to the Finance Committee on Tuesday, October 7, 2025.

Greg Komperda, the RNG Facility Project Manager, detailed a difficult summer for the plant, which converts landfill gas into pipeline-quality natural gas. While production in June exceeded its target, generating over 73,000 Million British Thermal Units (MMBtu), performance dipped significantly in July and August.

In July, the plant produced 68,768 MMBtu against a target of 71,300 MMBtu. August production fell further to 64,446 MMBtu. Komperda attributed the shortfalls to a string of problems, including:

  • Valve failures in the nitrogen removal system, likely caused by moisture in the compressed air supply.

  • A delivery rejection from the pipeline operator due to faulty sensors at the delivery point.

  • Ongoing landfill wellfield maintenance, which temporarily reduced the flow of gas to the plant.

  • Sporadic power outages caused by severe storms in late August.

  • Computer errors in the nitrogen control system that required the manufacturer to reprogram it.

Despite the setbacks, Komperda reported that production rebounded in September to over 69,000 MMBtu. “We are closing in on the gap,” he said. “If we could maintain production at a good level, we have a chance of closing that gap in on our under revenue.”

Board members questioned the operational reliability and long-term financial viability of the project. In response to questions about frequent power outages, officials stated that installing a backup generator system capable of powering the plant was not financially feasible. Similarly, a significant solar array to offset the plant’s high electricity consumption—more than all other county facilities combined—would require 70-80 acres and cost an estimated $28 to $48 million.

Board member Daniel J. Butler highlighted the project’s long-term investment perspective. He confirmed with officials that the plant was financed with a 12-year, $48 million green bond. With three years of payments made, the facility has nine years of debt service remaining.

“After 12 years, we are going to be having generate extra money and it should lessen the tax burden,” Butler said, framing the current challenges within the context of the plant’s projected 35-plus-year lifespan. “Here we are making an investment into the future for the people of Will County.”

Events

No events

Leave a Comment





Latest News Stories

Will-County-Public-Works-Transportation-Committee-Meeting-July-1-2025

Access Will County Dial-a-Ride Program Sees Record Growth, Eyes Expansion

Will County's dial-a-ride transportation service for seniors and disabled residents reached record ridership levels while officials plan major expansion to cover all county townships. The Access Will County program served...
Will-County-Capital-Improvements-IT-Committee-Meeting-July-1-2025

Will County to Launch New Public Meeting Agenda System in August Amidst Data Conversion Concerns

Will County is set to launch its new public meeting agenda and records software, Granicus “OneMeeting,” in August, but the transition will see over a decade of historical records converted...
Will-County-Planning-and-Zoning-Commission-Meeting-July-1-2025

Green Garden Township Poised for First Major Subdivision in Years After Rezoning

The Will County Planning and Zoning Commission has recommended a rezoning that could pave the way for the first major residential subdivision in Green Garden Township in nearly two decades....
Will-County-Finance-Committee-Meeting-July-1-2025

County RNG Facility Shows Strong Performance Despite Solar Challenges

Will County's Renewable Natural Gas facility is exceeding production targets while officials explore options to reduce substantial electricity costs that currently impact profitability. Project manager Greg Komperda told Finance Committee...
Meeting-Briefs

PZC Briefs: Solar Farm in Crete, Post-Fire Permit for Troy Business, and More

The Will County Planning and Zoning Commission handled several other cases during its July 1 meeting, including a new solar farm, a temporary permit for a fire-damaged business, and routine...
Meeting-Briefs

In Brief: Capital & IT News

Here are other highlights from the Will County Capital Improvements & IT Committee meeting on Tuesday. Successful Fire Drill at County BuildingThe Will County Office Building held its first full...
Meeting-Briefs

Will County Finance Committee July 1 Meeting Briefs

Bond Refinancing Advances: Finance Committee approved an ordinance authorizing up to $200.8 million in bond refinancing that could save taxpayers more than $716,000. The measure moves to the full County...
Meeting-Briefs

Will County Public Works Committee Juliy 1 Meeting Briefs

ROAD CONTRACTS APPROVED Austin Tyler Construction Contract: The committee approved a $691,544 contract with Austin Tyler Construction for resurfacing River Road from East Frontage Road to Prairie Creek Bridge and...
Screenshot 2025-07-08 at 2.34.06 PM

Green Garden Township Weighs Youth Sports Partnership for Community Development

Green Garden Township could become home to expanded youth football facilities under a proposal presented at Thursday's special meeting, as local sports programs seek permanent venues amid community facility discussions....
Meeting-Briefs-1

Green Garden Town Hall June 26 Meeting Briefs

Grant Deadline Approaches: Green Garden Township must decide on facility plans by the end of 2026 to retain $400,000 in remaining Will County grant funding. The township has already invested...
JJC-Graphic-Logo

JJC Trustees Approve Contentious FY26 Budget After Heated Debate, Failed Postponement

The Joliet Junior College Board of Trustees on Wednesday approved a $322.3 million budget for fiscal year 2026, but not before a tense debate that saw a motion to postpone...
Joliet-Junior-college.-Graphic-Logo.5

JJC’s ‘12x12x12’ Initiative Boosts College Credits, Increases Matriculation Rate

Joliet Junior College’s ambitious "12x12x12" initiative is yielding significant results, leading to more high school students earning college credits and a greater percentage of them choosing to attend JJC after...
Joliet-Junior-college.-Graphic-Logo.4

JJC Board Meeting Highlights Tensions Over Legal Bills, Trustee Conduct

An otherwise routine vote to approve monthly bill payments ignited a tense exchange at the Joliet Junior College Board of Trustees meeting Wednesday, revealing ongoing friction over redacted legal invoices,...
Joliet-Junior-college.-Graphic-Logo.3

Students, Trustees Emphasize Importance of Inclusivity and Flag Raisings at JJC

From a recent graduate’s public plea to trustee remarks on federal policies, the theme of student belonging and inclusivity was a prominent thread at the Joliet Junior College Board of...
Joliet-Junior-college.-Graphic-Logo.2

JJC Embarks on New 10-15 Year Facilities Master Plan Process

Joliet Junior College is laying the groundwork for its physical future, officially launching a comprehensive process to create a new facilities master plan that will guide campus development for the...