Lincoln-Way Community High School District 210 Meeting | December 18, 2025

Article Summary: The District 210 Board of Education awarded a $24.4 million bid to BEAR Construction Company for comprehensive mechanical and HVAC upgrades at Lincoln-Way Central and East high schools. The project is funded through life safety bonds approved in 2025 and is scheduled to be executed over the next two summers.

Mechanical Upgrades Key Points:

  • Total Contract Value: $24,419,400 awarded to BEAR Construction Company.

  • Equipment Direct Purchase: An additional $3,750,000 was approved for the direct purchase of mechanical equipment through the OMNIA co-op.

  • Timeline: The majority of the work at Lincoln-Way Central is slated for completion in the summer of 2026, with carryover work at both Central and East in 2027.

  • Budget Status: Total project projections, including fees and equipment, stand at $30,415,862, remaining within the $30,420,000 bond funding.

The Lincoln-Way Community High School District 210 Board of Education on Thursday, Dec. 18, 2025, moved forward with its massive life safety initiative by awarding a $24,419,400 bid for HVAC and mechanical upgrades.

The board selected BEAR Construction Company as the lowest qualified bidder for “Base Bid C,” which covers comprehensive work at both Lincoln-Way Central and Lincoln-Way East. The contract includes several alternates, such as the replacement of controls for existing equipment and the installation of conduit for new ComEd primary conductors at Lincoln-Way East.

District officials worked with DLA Architects to structure the bid process, eventually opting to “sole-source” or direct-purchase certain mechanical units through the OMNIA co-op to ensure proper fit and compliance with existing infrastructure. This equipment purchase, totaling $3.75 million from Thermosystems, was approved in a separate motion.

“We are right on budget in terms of life safety,” Assistant Superintendent Michael Duback told the board. “If there were any sort of unknown costs that exceed the life safety bond total, we will draw from budgeted capital projects funding.”

One remaining variable is the potential cost from ComEd related to switchgear upgrades, which is currently estimated at approximately $15,000.

Director of Buildings and Grounds Charles Welke has already begun scheduling meetings with the construction manager to finalize timelines. The plan prioritizes the bulk of the work at Central during the upcoming summer to minimize disruption to the 2026-27 school year.

Leave a Comment





Latest News Stories

D.C. Mayor Muriel Bowser won't seek reelection

D.C. Mayor Muriel Bowser won’t seek reelection

By Sarah Roderick-FitchThe Center Square Washington, D.C., Mayor Muriel Bowser announced she will not be seeking reelection. The Democratic mayor has served as the second female mayor of the nation’s...
Screenshot 2025-11-21 at 12.07.45 PM

Peotone School Board Approves Tentative Tax Levy, Advances $4.9M Bond Issuance

Peotone School Board Meeting | November 17, 2025 Article Summary:The Peotone School District 207-U Board of Education on Monday, November 17, 2025, approved a tentative $15.66 million tax levy and...
Illinois business group warns of 'backbreaking' progressive income tax

Illinois business group warns of ‘backbreaking’ progressive income tax

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – Manufacturers say legislators at the Illinois State Capitol have done enough damage and a progressive tax would...
Trump's ACA tax credit extension proposal delayed after GOP pushback

Trump’s ACA tax credit extension proposal delayed after GOP pushback

By Thérèse BoudreauxThe Center Square After facing backlash from Republican leaders, the White House is backing away from its proposal to extend the enhanced Obamacare Premium Tax Credit for two...
EXCLUSIVE: Texas rep calls on Trump to get Texan released from Mexican prison

EXCLUSIVE: Texas rep calls on Trump to get Texan released from Mexican prison

By Bethany BlankleyThe Center Square Texas state Rep. Jay Dean, R-Longview, is calling on President Donald Trump, Gov. Greg Abbott, Secretary of State Marco Rubio, U.S. Senators Ted Cruz and...
Illinois tops U.S. in pumpkin production despite recent decline in value

Illinois tops U.S. in pumpkin production despite recent decline in value

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Despite a recent decline in production value, Illinois is far and away the leader when it comes...
Congress moves to restore federal union powers, critics warn of higher costs

Congress moves to restore federal union powers, critics warn of higher costs

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – The U.S. Congress is set to vote on House Resolution 2550, a bill that would restore...
Blue Devil Logo Graphic

Warriors’ Defense Stifles Blue Devils in Lopsided Loss

PEOTONE — The Peotone Blue Devils endured a tough shooting night Friday, falling 52-20 to the Crete-Monee Warriors in non-conference girls basketball action. The Blue Devils (0-3) connected on just...
Illinois quick hits: Chiropractor sentenced for fraud; fatal airport shooting investigation

Illinois quick hits: Chiropractor sentenced for fraud; fatal airport shooting investigation

By Jim Talamonti | The Center SquareThe Center Square Chiropractor sentenced for fraud A Chicago chiropractor has been sentenced to nearly six years in federal prison for billing a private...
Screenshot 2025-11-21 at 10.19.55 AM

Lincoln-Way 210 Receives Clean Audit, Financial Profile Score Downgraded to ‘Review’

Lincoln-Way Community High School District 210 Meeting | November 20, 2025 Article Summary: Lincoln-Way District 210 received a clean, unmodified opinion for its Fiscal Year 2025 audit, the highest rating possible....
Will County P&Z Logo Planning Zoning.2

Committee Grants Lenox Solar Farm Project Six-Month Variance Extension

Will County Planning and Zoning Commission Meeting | November 18, 2025 Article Summary:The Will County Planning and Zoning Commission has approved a 180-day extension for variances tied to a commercial...
Will County Logo Graphic

Speed Limits Lowered in Green Garden and Frankfort Neighborhoods

Will County Board Meeting | November 2025 Article Summary: The Will County Board adopted ordinances to establish new, lower speed limits in specific areas of Green Garden and Frankfort Townships....
Will County Board Graphic.02

Engineering Firm Hired for Gougar Road Bridge Replacement

Will County Board Meeting | November 2025 Article Summary: The Will County Board authorized a $301,000 contract for the design of a new bridge carrying Gougar Road over the Canadian...
Will County Board Graphic.03

Unpermitted Log Cabin and Stage Prompt Rezoning in Beecher

Will County Board Meeting | November 2025 Article Summary: The Will County Board approved a zoning map amendment and variances for a property in Beecher to bring existing unpermitted structures...
Federal court blocks Trump from dismantling four agencies

Federal court blocks Trump from dismantling four agencies

By Dave Mason | The Center SquareThe Center Square (The Center Square) – A federal court has issued a permanent injunction stopping the Trump administration from dismantling four federal agencies...