Will County Partners with LNS Development for Laraway Road Drainage Improvements in New Lenox
Will County Public Works & Transportation Committee Meeting | April 7, 2026
Article Summary: The county approved a cost-sharing agreement with a private developer to build shared stormwater management facilities that will serve both a new residential subdivision and the upcoming Laraway Road widening project.
Laraway Road / LNS Development Key Points:
-
Will County and LNS Development Group, LLC will co-fund shared stormwater infrastructure.
-
The county will pay an estimated $332,209.92 for its share of the detention facility and storm sewer upgrades.
-
The county is also paying LNS Development $19,862.03 to acquire 0.43 acres of right-of-way required for the Laraway Road widening project.
-
The Laraway Road project will widen the highway to four lanes between Cedar Road and Spencer Road.
Will County is leveraging private development to streamline its own infrastructure costs, approving an agreement with LNS Development Group, LLC on Tuesday, April 7, 2026, to construct shared stormwater facilities along Laraway Road in New Lenox.
The agreement centers on a parcel of land (PIN 15-08-35-100-011) where LNS Development is planning a new residential subdivision. Concurrently, Will County is engineering a major capacity project to widen Laraway Road (County Highway 74) from a two-lane road to a four-lane highway with a center barrier median from Cedar Road to Spencer Road.
Because both the county’s highway expansion and the private residential development require significant stormwater management, the two entities agreed to co-locate and share the costs of a detention facility and upgraded storm sewers on the developer’s parcel.
According to the engineer’s estimates provided in the agenda packet, Will County’s financial obligation for the construction of the shared improvements is capped at an estimated $332,209.92. This breaks down to $179,218.92 (21% of the total cost) for the detention basin, and $152,991.00 (100% of the required upgrades) to properly size the storm sewers to accommodate WCDOT drainage. LNS Development will cover the remaining construction costs.
Furthermore, the agreement secures the land Will County needs to physically widen the road. LNS Development will convey 0.43668 acres of right-of-way to the county in exchange for $19,862.03. In return, the county guarantees the developer’s vested rights to specific access points and drainage capacity along the newly widened highway.
The measure was passed unanimously and advances to the full County Board.
Latest News Stories
Trump administration begins axing positions of furloughed federal workers
Fiscal Fallout: Illinois has among highest-paid state employees
Report: State reliance on federal funds up significantly since 1990s
Southwest low on list of safest states; Northeast at the top
Washington state attorney general agrees to protect seal of confession
Pacific Northwest journalists sound off on Antifa at President Trump’s roundtable
Nvidia will pay 100k visa fees, others unsure
‘Shameful:’ GOP leaders frustrated with Dems on tenth day of shutdown
Trump snubbed by Nobel Committee, praised by winner
Will County Committee Approves Preliminary $161.6M Tax Levy on Split Vote Amid Heated Debate Over Spending
Will County Eyes Major Overhaul to Consolidate Scattered Government Offices
Trump threatens tariffs on China over ‘hostile’ rare earths policy
Illinois legislator urges school discipline to focus on behavior, not race
WATCH: Trump appeals Guard TRO as DHS looks to ‘double down’ law enforcement in Chicago